TA-26-027 · Goodman Fielder Demo Collision detection retrofit — bakery palletisers ×6
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-027

TA-26-027

Complete On track

Collision detection retrofit — bakery palletisers ×6 · Goodman Fielder · Collision detection

Value
$24,800
budget cost $18k
Cost to date
$13,623
$9k parts · $4k labour
Forecast margin
25.4%
$6,309
Claimed
100%
$24,800 of $24,800
FAT
19 Aug
signed off
Parts short
0
BOM covered
Bill of materials
3 lines · $9,294 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
M12-5P-5M M12 5-pin cable, 5 m, PUR
Electrical · 72 ea free
6 6 — — $24.00 $144
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
6 6 — — $1,380.00 $8,280
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
6 6 — — $145.00 $870
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 20 Jul 2026 04 Aug 2026 12 Priya Raman
Procurement Procurement 30 Jul 2026 12 Aug 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 07 Aug 2026 18 Aug 2026 8 Ben Nguyen
Assembly Gripper assembly bench 12 Aug 2026 18 Aug 2026 5 Tom Kowalski
Controls Controls & robot programming 14 Aug 2026 19 Aug 2026 4 Luke Brennan
FAT FAT cell 19 Aug 2026 20 Aug 2026 2 Matt O'Connor
Commissioning Site crew 02 Sep 2026 04 Sep 2026 3 Steve Hargreaves
Time booked
49.0 h · $4,329 at cost rates
Luke Brennan13.5 h · $1,418
Priya Raman13.5 h · $1,215
Ryan Walsh7.5 h · $540
Steve Hargreaves6.5 h · $572
Tom Kowalski4.0 h · $288
Ben Nguyen4.0 h · $296
DateWhoTaskHoursCost
06 Oct 2026Steve HargreavesSite commissioning 0.5$44
06 Oct 2026Steve HargreavesSite commissioning 6.0$528
09 Sep 2026Luke BrennanFAT 3.0$315
31 Aug 2026Luke BrennanPLC & robot programming 7.5$788
27 Aug 2026Tom KowalskiMechanical assembly 4.0$288
26 Aug 2026Ryan WalshMechanical assembly 7.5$540
18 Aug 2026Ben NguyenMachining & fit-up 4.0$296
22 Jul 2026Luke BrennanControls design 3.0$315
22 Jul 2026Priya RamanMechanical design 5.5$495
21 Jul 2026Priya RamanMechanical design 8.0$720
Project
Customer
Goodman Fielder
Stephen Walker · Maintenance Engineer
Site
Goodman Fielder — Erskine Park
Robot
ABB IRB 660 (existing)
PM
Sebastian
Quote
Q-26-0049
Customer PO
GOO-PO-4575576
Key dates
Start
20 Jul 2026
FAT
19 Aug 2026
Ship
24 Aug 2026
Commissioning
02 Sep 2026
Completed
02 Sep 2026
Money
Value
$24,800
Budget cost
$18,491
Parts committed
$9,294
Parts issued
$9,294
Labour to date
$4,329
Forecast cost
$18,491
Forecast margin
$6,309 · 25.4%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0049 won — project TA-26-027 opened.
17 Jul, 10:18am · Aiden Clarke