Projects / TA-26-027
TA-26-027
Complete On trackCollision detection retrofit — bakery palletisers ×6 · Goodman Fielder · Collision detection
Value
$24,800
budget cost $18k
Cost to date
$13,623
$9k parts · $4k labour
Forecast margin
25.4%
$6,309
Claimed
100%
$24,800 of $24,800
FAT
19 Aug
signed off
Parts short
0
BOM covered
Bill of materials
3 lines · $9,294 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| M12-5P-5M | M12 5-pin cable, 5 m, PUR Electrical · 72 ea free | 6 | 6 | — | — | $24.00 | $144 | |
| TRK-CSS-L | Compliance shock sensor — large (≤300 kg tooling) Trak products · 0 ea free | 6 | 6 | — | — | $1,380.00 | $8,280 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 6 | 6 | — | — | $145.00 | $870 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 20 Jul 2026 | 04 Aug 2026 | 12 | Priya Raman | |
| Procurement | Procurement | 30 Jul 2026 | 12 Aug 2026 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 07 Aug 2026 | 18 Aug 2026 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 12 Aug 2026 | 18 Aug 2026 | 5 | Tom Kowalski | |
| Controls | Controls & robot programming | 14 Aug 2026 | 19 Aug 2026 | 4 | Luke Brennan | |
| FAT | FAT cell | 19 Aug 2026 | 20 Aug 2026 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 02 Sep 2026 | 04 Sep 2026 | 3 | Steve Hargreaves |
Time booked
49.0 h · $4,329 at cost rates
Luke Brennan13.5 h · $1,418
Priya Raman13.5 h · $1,215
Ryan Walsh7.5 h · $540
Steve Hargreaves6.5 h · $572
Tom Kowalski4.0 h · $288
Ben Nguyen4.0 h · $296
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 06 Oct 2026 | Steve Hargreaves | Site commissioning | 0.5 | $44 | |
| 06 Oct 2026 | Steve Hargreaves | Site commissioning | 6.0 | $528 | |
| 09 Sep 2026 | Luke Brennan | FAT | 3.0 | $315 | |
| 31 Aug 2026 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 27 Aug 2026 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 26 Aug 2026 | Ryan Walsh | Mechanical assembly | 7.5 | $540 | |
| 18 Aug 2026 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 22 Jul 2026 | Luke Brennan | Controls design | 3.0 | $315 | |
| 22 Jul 2026 | Priya Raman | Mechanical design | 5.5 | $495 | |
| 21 Jul 2026 | Priya Raman | Mechanical design | 8.0 | $720 |
Project
- Customer
- Goodman FielderStephen Walker · Maintenance Engineer
- Site
- Goodman Fielder — Erskine Park
- Robot
- ABB IRB 660 (existing)
- PM
- Sebastian
- Quote
- Q-26-0049
- Customer PO
- GOO-PO-4575576
Key dates
- Start
- 20 Jul 2026
- FAT
- 19 Aug 2026
- Ship
- 24 Aug 2026
- Commissioning
- 02 Sep 2026
- Completed
- 02 Sep 2026
Money
- Value
- $24,800
- Budget cost
- $18,491
- Parts committed
- $9,294
- Parts issued
- $9,294
- Labour to date
- $4,329
- Forecast cost
- $18,491
- Forecast margin
- $6,309 · 25.4%
Purchase orders
All POsNo purchase orders for this project.
Calendar
CalendarNothing in the calendar.
Activity
Quote Q-26-0049 won — project TA-26-027 opened.
17 Jul, 10:18am · Aiden Clarke