Projects / TA-26-041
TA-26-041
Fabrication On trackCustom tooling — battery tray handling EOAT · Bosch Manufacturing Solutions · Custom tooling
Value
$54,800
budget cost $35k
Cost to date
$7,117
$2k parts · $6k labour
Forecast margin
35.7%
$19,537
Claimed
30%
$16,440 of $54,800
FAT
21 Oct
in 15 days
Parts short
0
BOM covered
Bill of materials
8 lines · $7,287 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| SHCS-M8-25 | Socket head cap screw M8 × 25, 12.9 (box 100) Fasteners · 18 box free | 1 | 1 | — | — | $34.00 | $34 | |
| AL6061-PL10 | Aluminium plate 6061-T6, 10 mm, 2400 × 1200 Raw material · 7 sheet free | 1 | 1 | — | — | $640.00 | $640 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 6 | — | 6 | — | $58.00 | $348 | |
| TRK-CSS-S | Compliance shock sensor — small (≤50 kg tooling) Trak products · 10 ea free | 1 | 1 | — | — | $760.00 | $760 | |
| TRK-MP-FAN | Sensor mounting plate — FANUC flange Trak products · 8 ea free | 1 | 1 | — | — | $145.00 | $145 | |
| GPP5008N-00-A | Zimmer GPP5008N pneumatic parallel gripper Zimmer components · 10 ea free | 4 | — | 4 | — | $640.00 | $2,560 | |
| MKS1501A | Zimmer MKS1501A linear clamping element Zimmer components · 13 ea free | 4 | — | 4 | — | $310.00 | $1,240 | |
| WWR1600-B | Zimmer WWR1600 quick-change system Zimmer components · 4 ea free | 1 | — | 1 | — | $1,560.00 | $1,560 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $16,44030% of $54,800
Deposit 30%
INV-10466
$16,440 ex GST · $18,084 inc
Awaiting paymentXero synced
FAT 40%
$21,920
not raised
Commissioning 30%
$16,440
not raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 31 Aug 2026 | 15 Sep 2026 | 12 | Daniel Pham | |
| Procurement | Procurement | 10 Sep 2026 | 23 Sep 2026 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 18 Sep 2026 | 29 Sep 2026 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 05 Oct 2026 | 20 Oct 2026 | 12 | Tom Kowalski | |
| Controls | Controls & robot programming | 12 Oct 2026 | 21 Oct 2026 | 8 | Luke Brennan | |
| FAT | FAT cell | 21 Oct 2026 | 22 Oct 2026 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 29 Oct 2026 | 02 Nov 2026 | 3 | Steve Hargreaves |
Time booked
59.5 h · $5,538 at cost rates
Daniel Pham35.0 h · $3,325
Priya Raman7.5 h · $675
Ben Nguyen7.0 h · $518
Josh Mitchell6.0 h · $600
Luke Brennan4.0 h · $420
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 28 Sep 2026 | Ben Nguyen | Machining & fit-up | 7.0 | $518 | |
| 08 Sep 2026 | Daniel Pham | Mechanical design | 1.0 | $95 | |
| 07 Sep 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 04 Sep 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 03 Sep 2026 | Josh Mitchell | Controls design | 6.0 | $600 | |
| 03 Sep 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 02 Sep 2026 | Luke Brennan | Controls design | 4.0 | $420 | |
| 02 Sep 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 01 Sep 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 31 Aug 2026 | Daniel Pham | Mechanical design | 6.0 | $570 |
Project
- Customer
- Bosch Manufacturing SolutionsJürgen Albers · Engineering Manager
- Site
- Bosch Manufacturing Solutions — Clayton
- Robot
- ABB IRB 660 (existing)
- PM
- Sebastian
- Quote
- Q-26-0059
- Customer PO
- BOS-PO-4565385
Key dates
- Start
- 31 Aug 2026
- FAT
- 21 Oct 2026
- Ship
- 26 Oct 2026
- Commissioning
- 29 Oct 2026
Money
- Value
- $54,800
- Budget cost
- $35,263
- Parts committed
- $7,287
- Parts issued
- $1,579
- Labour to date
- $5,538
- Forecast cost
- $35,263
- Forecast margin
- $19,537 · 35.7%
Purchase orders
All POsCalendar
CalendarActivity
Quote Q-26-0059 won — project TA-26-041 opened.
23 Aug, 10:36am · Craig Kirkpatrick