TA-26-041 · Bosch Manufacturing Solutions Demo Custom tooling — battery tray handling EOAT
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-041

TA-26-041

Fabrication On track

Custom tooling — battery tray handling EOAT · Bosch Manufacturing Solutions · Custom tooling

Value
$54,800
budget cost $35k
Cost to date
$7,117
$2k parts · $6k labour
Forecast margin
35.7%
$19,537
Claimed
30%
$16,440 of $54,800
FAT
21 Oct
in 15 days
Parts short
0
BOM covered
Bill of materials
8 lines · $7,287 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
SHCS-M8-25 Socket head cap screw M8 × 25, 12.9 (box 100)
Fasteners · 18 box free
1 1 — — $34.00 $34
AL6061-PL10 Aluminium plate 6061-T6, 10 mm, 2400 × 1200
Raw material · 7 sheet free
1 1 — — $640.00 $640
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
6 — 6 — $58.00 $348
TRK-CSS-S Compliance shock sensor — small (≤50 kg tooling)
Trak products · 10 ea free
1 1 — — $760.00 $760
TRK-MP-FAN Sensor mounting plate — FANUC flange
Trak products · 8 ea free
1 1 — — $145.00 $145
GPP5008N-00-A Zimmer GPP5008N pneumatic parallel gripper
Zimmer components · 10 ea free
4 — 4 — $640.00 $2,560
MKS1501A Zimmer MKS1501A linear clamping element
Zimmer components · 13 ea free
4 — 4 — $310.00 $1,240
WWR1600-B Zimmer WWR1600 quick-change system
Zimmer components · 4 ea free
1 — 1 — $1,560.00 $1,560
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $16,44030% of $54,800
Deposit 30%
INV-10466
$16,440 ex GST · $18,084 inc
Awaiting paymentXero synced
FAT 40%
$21,920
not raised
Commissioning 30%
$16,440
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 31 Aug 2026 15 Sep 2026 12 Daniel Pham
Procurement Procurement 10 Sep 2026 23 Sep 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 18 Sep 2026 29 Sep 2026 8 Ben Nguyen
Assembly Gripper assembly bench 05 Oct 2026 20 Oct 2026 12 Tom Kowalski
Controls Controls & robot programming 12 Oct 2026 21 Oct 2026 8 Luke Brennan
FAT FAT cell 21 Oct 2026 22 Oct 2026 2 Matt O'Connor
Commissioning Site crew 29 Oct 2026 02 Nov 2026 3 Steve Hargreaves
Time booked
59.5 h · $5,538 at cost rates
Daniel Pham35.0 h · $3,325
Priya Raman7.5 h · $675
Ben Nguyen7.0 h · $518
Josh Mitchell6.0 h · $600
Luke Brennan4.0 h · $420
DateWhoTaskHoursCost
28 Sep 2026Ben NguyenMachining & fit-up 7.0$518
08 Sep 2026Daniel PhamMechanical design 1.0$95
07 Sep 2026Daniel PhamMechanical design 8.0$760
04 Sep 2026Daniel PhamMechanical design 4.0$380
03 Sep 2026Josh MitchellControls design 6.0$600
03 Sep 2026Priya RamanMechanical design 7.5$675
02 Sep 2026Luke BrennanControls design 4.0$420
02 Sep 2026Daniel PhamMechanical design 8.0$760
01 Sep 2026Daniel PhamMechanical design 8.0$760
31 Aug 2026Daniel PhamMechanical design 6.0$570
Project
Customer
Bosch Manufacturing Solutions
Jürgen Albers · Engineering Manager
Site
Bosch Manufacturing Solutions — Clayton
Robot
ABB IRB 660 (existing)
PM
Sebastian
Quote
Q-26-0059
Customer PO
BOS-PO-4565385
Key dates
Start
31 Aug 2026
FAT
21 Oct 2026
Ship
26 Oct 2026
Commissioning
29 Oct 2026
Money
Value
$54,800
Budget cost
$35,263
Parts committed
$7,287
Parts issued
$1,579
Labour to date
$5,538
Forecast cost
$35,263
Forecast margin
$19,537 · 35.7%
Purchase orders
All POs
Calendar
Calendar
Activity
Quote Q-26-0059 won — project TA-26-041 opened.