TA-25-028 · Incitec Pivot Fertilisers Demo Fork palletising gripper — 25 kg fertiliser bags
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-25-028

TA-25-028

Complete On track

Fork palletising gripper — 25 kg fertiliser bags · Incitec Pivot Fertilisers · Fork palletising

Value
$84,500
budget cost $57k
Cost to date
$33,729
$9k parts · $25k labour
Forecast margin
32.8%
$27,738
Claimed
100%
$84,500 of $84,500
FAT
17 Dec
signed off
Parts short
0
BOM covered
Bill of materials
10 lines · $8,585 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CMP71S-KH4 SEW CMP71S synchronous servomotor
Drives & controls · 1 ea free
1 1 — — $2,120.00 $2,120
M12-5P-5M M12 5-pin cable, 5 m, PUR
Electrical · 72 ea free
6 6 — — $24.00 $144
SHCS-M10-30 Socket head cap screw M10 × 30, 12.9 (box 50)
Fasteners · 15 box free
1 1 — — $38.00 $38
DSBC-50-200-PPVA Festo DSBC standard cylinder Ø50 × 200
Pneumatics · 10 ea free
2 2 — — $268.00 $536
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
10 10 — — $21.00 $210
AL6061-PL20 Aluminium plate 6061-T6, 20 mm, 2400 × 1200
Raw material · 4 sheet free
1 1 — — $1,260.00 $1,260
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
4 4 — — $58.00 $232
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
1 1 — — $1,380.00 $1,380
TRK-FRK-CF11 Carbon fibre flat fork tine — 1100 mm
Trak products · 13 ea free
6 6 — — $420.00 $2,520
TRK-MP-FAN Sensor mounting plate — FANUC flange
Trak products · 8 ea free
1 1 — — $145.00 $145
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 06 Oct 2025 21 Oct 2025 12 Daniel Pham
Procurement Procurement 16 Oct 2025 29 Oct 2025 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 24 Oct 2025 04 Nov 2025 8 Ben Nguyen
Assembly Gripper assembly bench 01 Dec 2025 16 Dec 2025 12 Tom Kowalski
Controls Controls & robot programming 08 Dec 2025 17 Dec 2025 8 Josh Mitchell
FAT FAT cell 17 Dec 2025 18 Dec 2025 2 Matt O'Connor
Commissioning Site crew 21 Jan 2026 23 Jan 2026 3 Steve Hargreaves
Time booked
280.0 h · $25,144 at cost rates
Luke Brennan66.5 h · $6,983
Daniel Pham42.0 h · $3,990
Tom Kowalski36.0 h · $2,592
Priya Raman35.5 h · $3,195
Josh Mitchell34.0 h · $3,400
Ryan Walsh29.5 h · $2,124
Ben Nguyen24.0 h · $1,776
Steve Hargreaves10.5 h · $924
Matt O'Connor2.0 h · $160
DateWhoTaskHoursCost
31 Dec 2025Steve HargreavesSite commissioning 0.5$44
30 Dec 2025Luke BrennanSite commissioning 7.5$788
29 Dec 2025Steve HargreavesSite commissioning 6.0$528
26 Dec 2025Steve HargreavesSite commissioning 4.0$352
25 Dec 2025Luke BrennanSite commissioning 4.0$420
24 Dec 2025Luke BrennanSite commissioning 6.0$630
23 Dec 2025Luke BrennanSite commissioning 7.5$788
28 Nov 2025Matt O'ConnorFAT 2.0$160
27 Nov 2025Luke BrennanFAT 8.0$840
26 Nov 2025Luke BrennanFAT 4.0$420
26 Nov 2025Tom KowalskiMechanical assembly 5.0$360
25 Nov 2025Luke BrennanFAT 4.0$420
25 Nov 2025Josh MitchellPLC & robot programming 8.0$800
25 Nov 2025Tom KowalskiMechanical assembly 8.0$576
24 Nov 2025Josh MitchellPLC & robot programming 4.0$400
24 Nov 2025Ryan WalshMechanical assembly 6.0$432
21 Nov 2025Josh MitchellPLC & robot programming 6.0$600
21 Nov 2025Tom KowalskiMechanical assembly 7.5$540
20 Nov 2025Luke BrennanPLC & robot programming 7.5$788
20 Nov 2025Ryan WalshMechanical assembly 8.0$576
19 Nov 2025Josh MitchellPLC & robot programming 4.0$400
19 Nov 2025Ryan WalshMechanical assembly 7.5$540
18 Nov 2025Luke BrennanPLC & robot programming 8.0$840
18 Nov 2025Tom KowalskiMechanical assembly 7.5$540
17 Nov 2025Luke BrennanPLC & robot programming 4.0$420
17 Nov 2025Tom KowalskiMechanical assembly 8.0$576
14 Nov 2025Ryan WalshMechanical assembly 8.0$576
07 Nov 2025Ben NguyenMachining & fit-up 2.0$148
06 Nov 2025Ben NguyenMachining & fit-up 4.0$296
05 Nov 2025Ben NguyenMachining & fit-up 4.0$296
04 Nov 2025Ben NguyenMachining & fit-up 4.0$296
03 Nov 2025Ben NguyenMachining & fit-up 6.0$444
31 Oct 2025Ben NguyenMachining & fit-up 4.0$296
27 Oct 2025Daniel PhamMechanical design 2.5$238
24 Oct 2025Daniel PhamMechanical design 4.0$380
23 Oct 2025Daniel PhamMechanical design 8.0$760
22 Oct 2025Daniel PhamMechanical design 6.0$570
21 Oct 2025Priya RamanMechanical design 6.0$540
20 Oct 2025Priya RamanMechanical design 4.0$360
17 Oct 2025Daniel PhamMechanical design 7.5$713
16 Oct 2025Daniel PhamMechanical design 6.0$570
15 Oct 2025Priya RamanMechanical design 7.5$675
14 Oct 2025Priya RamanMechanical design 8.0$720
13 Oct 2025Daniel PhamMechanical design 8.0$760
10 Oct 2025Priya RamanMechanical design 4.0$360
09 Oct 2025Josh MitchellControls design 4.5$450
09 Oct 2025Priya RamanMechanical design 6.0$540
08 Oct 2025Luke BrennanControls design 6.0$630
07 Oct 2025Josh MitchellControls design 7.5$750
Project
Customer
Incitec Pivot Fertilisers
Kieran Dunne · Site Engineer
Site
Incitec Pivot Fertilisers — North Geelong
Robot
FANUC M-410iC (existing)
PM
Sebastian
Quote
Q-25-0064
Customer PO
INC-PO-4585249
Key dates
Start
06 Oct 2025
FAT
17 Dec 2025
Ship
12 Jan 2026
Commissioning
21 Jan 2026
Completed
21 Jan 2026
Money
Value
$84,500
Budget cost
$56,762
Parts committed
$8,585
Parts issued
$8,585
Labour to date
$25,144
Forecast cost
$56,762
Forecast margin
$27,738 · 32.8%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-25-0064 won — project TA-25-028 opened.
3 Oct, 10:53am · Aiden Clarke