Trak
Trak
TA-26-002 · Visy Paper — Coolaroo Demo Reel handling — core bung inserter & trimmer cell
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-002

TA-26-002

Complete On track

Reel handling — core bung inserter & trimmer cell · Visy Paper — Coolaroo · Reel handling — core bung & trimmer

Value
$512,000
budget cost $353k
Cost to date
$263,528
$155k parts · $108k labour
Forecast margin
31.0%
$158,758
Claimed
100%
$512,000 of $512,000
FAT
18 Feb
signed off
Parts short
0
BOM covered
Bill of materials
14 lines · $155,409 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CX5130-0125 Beckhoff CX5130 embedded PC (TwinCAT)
Drives & controls · 4 ea free
1 1 — — $2,480.00 $2,480
ENC-600-SS Control enclosure 600 × 600, stainless
Electrical · 2 ea free
1 1 — — $920.00 $920
IRB660-250 ABB IRB 660 palletising robot, 250 kg / 3.15 m
Robots · 0 ea free
1 1 — — $118,600.00 $118,600
C4P-SA15030A SICK deTec4 safety light curtain 1500 mm
Sensors & safety · 4 pair free
2 2 — — $2,140.00 $4,280
INSPECTORP621 SICK InspectorP621 vision sensor
Sensors & safety · 0 ea free
1 1 — — $3,890.00 $3,890
PNOZ-MB0 Pilz PNOZmulti 2 safety relay base unit
Sensors & safety · 4 ea free
1 1 — — $1,180.00 $1,180
XG-DOOR-SL Axelent sliding door kit with interlock
Sensors & safety · 2 ea free
1 1 — — $1,450.00 $1,450
XG-PANEL-2200 Axelent X-Guard mesh panel 2200 × 1500
Sensors & safety · 36 ea free
16 16 — — $168.00 $2,688
XG-POST-2200 Axelent X-Guard post 2200
Sensors & safety · 36 ea free
14 14 — — $64.00 $896
TRK-CBI-HD Core bung inserter head — pneumatic
Trak products · 2 ea free
1 1 — — $7,400.00 $7,400
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
1 1 — — $1,380.00 $1,380
TRK-CUT-QC Quick-change core cutter head
Trak products · 4 ea free
2 2 — — $2,150.00 $4,300
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
1 1 — — $145.00 $145
SIDECH-2BH19 Side channel blower 2BH1 9.5 kW
Vacuum · 1 ea free
1 1 — — $5,800.00 $5,800
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 20 Oct 2025 14 Nov 2025 20 Daniel Pham
Procurement Procurement 07 Nov 2025 27 Nov 2025 15 Jess Taylor
Fabrication Excelfab — laser, fold & weld 20 Nov 2025 05 Dec 2025 12 Ben Nguyen
Assembly Assembly bay 1 19 Jan 2026 17 Feb 2026 22 Tom Kowalski
Controls Controls & robot programming 30 Jan 2026 19 Feb 2026 15 Josh Mitchell
FAT FAT cell 18 Feb 2026 20 Feb 2026 3 Matt O'Connor
Commissioning Site crew 23 Mar 2026 01 Apr 2026 8 Steve Hargreaves
Time booked
1,207.0 h · $108,119 at cost rates
Luke Brennan284.0 h · $29,820
Daniel Pham211.5 h · $20,093
Tom Kowalski156.5 h · $11,268
Ryan Walsh126.0 h · $9,072
Josh Mitchell123.0 h · $12,300
Priya Raman122.5 h · $11,025
Ben Nguyen102.5 h · $7,585
Steve Hargreaves59.5 h · $5,236
Matt O'Connor21.5 h · $1,720
DateWhoTaskHoursCost
10 Feb 2026Luke BrennanSite commissioning 5.5$578
09 Feb 2026Steve HargreavesSite commissioning 8.0$704
06 Feb 2026Luke BrennanSite commissioning 6.0$630
05 Feb 2026Luke BrennanSite commissioning 4.0$420
04 Feb 2026Steve HargreavesSite commissioning 4.0$352
03 Feb 2026Steve HargreavesSite commissioning 6.0$528
02 Feb 2026Luke BrennanSite commissioning 4.0$420
02 Feb 2026Ryan WalshMechanical assembly 4.5$324
30 Jan 2026Steve HargreavesSite commissioning 6.0$528
30 Jan 2026Tom KowalskiMechanical assembly 8.0$576
29 Jan 2026Luke BrennanSite commissioning 8.0$840
29 Jan 2026Tom KowalskiMechanical assembly 4.0$288
28 Jan 2026Luke BrennanSite commissioning 7.5$788
28 Jan 2026Tom KowalskiMechanical assembly 7.5$540
27 Jan 2026Steve HargreavesSite commissioning 7.5$660
27 Jan 2026Ryan WalshMechanical assembly 8.0$576
26 Jan 2026Steve HargreavesSite commissioning 6.0$528
26 Jan 2026Ryan WalshMechanical assembly 8.0$576
23 Jan 2026Luke BrennanSite commissioning 6.0$630
23 Jan 2026Ryan WalshMechanical assembly 6.0$432
22 Jan 2026Luke BrennanSite commissioning 8.0$840
22 Jan 2026Tom KowalskiMechanical assembly 4.0$288
21 Jan 2026Luke BrennanSite commissioning 4.0$420
21 Jan 2026Tom KowalskiMechanical assembly 6.0$432
20 Jan 2026Steve HargreavesSite commissioning 8.0$704
20 Jan 2026Tom KowalskiMechanical assembly 6.0$432
19 Jan 2026Steve HargreavesSite commissioning 6.0$528
19 Jan 2026Tom KowalskiMechanical assembly 4.0$288
16 Jan 2026Luke BrennanSite commissioning 8.0$840
16 Jan 2026Ryan WalshMechanical assembly 4.0$288
15 Jan 2026Luke BrennanSite commissioning 6.0$630
15 Jan 2026Ryan WalshMechanical assembly 8.0$576
14 Jan 2026Steve HargreavesSite commissioning 4.0$352
14 Jan 2026Tom KowalskiMechanical assembly 7.5$540
13 Jan 2026Steve HargreavesSite commissioning 4.0$352
13 Jan 2026Ryan WalshMechanical assembly 4.0$288
12 Jan 2026Luke BrennanSite commissioning 4.0$420
12 Jan 2026Luke BrennanPLC & robot programming 1.5$158
12 Jan 2026Tom KowalskiMechanical assembly 6.0$432
09 Jan 2026Luke BrennanSite commissioning 8.0$840
09 Jan 2026Josh MitchellPLC & robot programming 7.5$750
09 Jan 2026Ryan WalshMechanical assembly 4.0$288
08 Jan 2026Luke BrennanSite commissioning 7.5$788
08 Jan 2026Josh MitchellPLC & robot programming 6.0$600
08 Jan 2026Ryan WalshMechanical assembly 6.0$432
07 Jan 2026Luke BrennanSite commissioning 8.0$840
07 Jan 2026Luke BrennanPLC & robot programming 6.0$630
07 Jan 2026Ryan WalshMechanical assembly 6.0$432
06 Jan 2026Luke BrennanPLC & robot programming 7.5$788
06 Jan 2026Tom KowalskiMechanical assembly 7.5$540
05 Jan 2026Josh MitchellPLC & robot programming 6.0$600
05 Jan 2026Ryan WalshMechanical assembly 4.0$288
02 Jan 2026Luke BrennanPLC & robot programming 8.0$840
02 Jan 2026Tom KowalskiMechanical assembly 6.0$432
01 Jan 2026Josh MitchellPLC & robot programming 7.5$750
01 Jan 2026Tom KowalskiMechanical assembly 7.5$540
31 Dec 2025Luke BrennanPLC & robot programming 4.0$420
31 Dec 2025Tom KowalskiMechanical assembly 4.0$288
31 Dec 2025Priya RamanMechanical design 1.0$90
30 Dec 2025Luke BrennanPLC & robot programming 4.0$420
Project
Customer
Visy Paper — Coolaroo
Wayne Collins · Mill Maintenance Superintendent
Site
Visy Paper — Coolaroo
Robot
ABB IRB 660
PM
Sebastian
Quote
Q-26-0041
Customer PO
VIS-PO-4571787
Key dates
Start
20 Oct 2025
FAT
18 Feb 2026
Ship
25 Feb 2026
Commissioning
23 Mar 2026
Completed
23 Mar 2026
Money
Value
$512,000
Budget cost
$353,242
Parts committed
$155,409
Parts issued
$155,409
Labour to date
$108,119
Forecast cost
$353,242
Forecast margin
$158,758 · 31.0%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0041 won — project TA-26-002 opened.
14 Oct, 10:19am · Craig Kirkpatrick