TA-26-024 · Cement Australia — Railton Demo Fork palletising gripper — cement bags
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-024

TA-26-024

Complete On track

Fork palletising gripper — cement bags · Cement Australia — Railton · Fork palletising

Value
$79,200
budget cost $56k
Cost to date
$32,469
$9k parts · $24k labour
Forecast margin
29.4%
$23,281
Claimed
100%
$79,200 of $79,200
FAT
5 Aug
signed off
Parts short
0
BOM covered
Bill of materials
10 lines · $8,585 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CMP71S-KH4 SEW CMP71S synchronous servomotor
Drives & controls · 1 ea free
1 1 — — $2,120.00 $2,120
M12-5P-5M M12 5-pin cable, 5 m, PUR
Electrical · 72 ea free
6 6 — — $24.00 $144
SHCS-M10-30 Socket head cap screw M10 × 30, 12.9 (box 50)
Fasteners · 15 box free
1 1 — — $38.00 $38
DSBC-50-200-PPVA Festo DSBC standard cylinder Ø50 × 200
Pneumatics · 10 ea free
2 2 — — $268.00 $536
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
10 10 — — $21.00 $210
AL6061-PL20 Aluminium plate 6061-T6, 20 mm, 2400 × 1200
Raw material · 4 sheet free
1 1 — — $1,260.00 $1,260
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
4 4 — — $58.00 $232
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
1 1 — — $1,380.00 $1,380
TRK-FRK-CF11 Carbon fibre flat fork tine — 1100 mm
Trak products · 13 ea free
6 6 — — $420.00 $2,520
TRK-MP-FAN Sensor mounting plate — FANUC flange
Trak products · 8 ea free
1 1 — — $145.00 $145
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 25 May 2026 09 Jun 2026 12 Daniel Pham
Procurement Procurement 04 Jun 2026 17 Jun 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 12 Jun 2026 23 Jun 2026 8 Ben Nguyen
Assembly Gripper assembly bench 20 Jul 2026 04 Aug 2026 12 Ryan Walsh
Controls Controls & robot programming 27 Jul 2026 05 Aug 2026 8 Josh Mitchell
FAT FAT cell 05 Aug 2026 06 Aug 2026 2 Matt O'Connor
Commissioning Site crew 26 Aug 2026 28 Aug 2026 3 Steve Hargreaves
Time booked
269.0 h · $23,884 at cost rates
Luke Brennan59.5 h · $6,248
Priya Raman47.5 h · $4,275
Tom Kowalski38.0 h · $2,736
Daniel Pham27.0 h · $2,565
Josh Mitchell25.5 h · $2,550
Ryan Walsh25.0 h · $1,800
Ben Nguyen23.0 h · $1,702
Steve Hargreaves16.0 h · $1,408
Matt O'Connor7.5 h · $600
DateWhoTaskHoursCost
17 Aug 2026Luke BrennanSite commissioning 0.5$53
14 Aug 2026Luke BrennanSite commissioning 6.0$630
13 Aug 2026Steve HargreavesSite commissioning 4.0$352
12 Aug 2026Steve HargreavesSite commissioning 4.0$352
11 Aug 2026Luke BrennanSite commissioning 8.0$840
10 Aug 2026Steve HargreavesSite commissioning 8.0$704
07 Aug 2026Luke BrennanSite commissioning 4.0$420
20 Jul 2026Luke BrennanFAT 2.0$210
20 Jul 2026Ryan WalshMechanical assembly 5.0$360
17 Jul 2026Luke BrennanFAT 7.5$788
17 Jul 2026Ryan WalshMechanical assembly 6.0$432
16 Jul 2026Matt O'ConnorFAT 7.5$600
16 Jul 2026Ryan WalshMechanical assembly 4.0$288
15 Jul 2026Tom KowalskiMechanical assembly 8.0$576
14 Jul 2026Tom KowalskiMechanical assembly 4.0$288
13 Jul 2026Ryan WalshMechanical assembly 6.0$432
10 Jul 2026Luke BrennanPLC & robot programming 0.5$53
10 Jul 2026Tom KowalskiMechanical assembly 6.0$432
09 Jul 2026Josh MitchellPLC & robot programming 4.0$400
09 Jul 2026Tom KowalskiMechanical assembly 6.0$432
08 Jul 2026Josh MitchellPLC & robot programming 4.0$400
08 Jul 2026Tom KowalskiMechanical assembly 6.0$432
07 Jul 2026Luke BrennanPLC & robot programming 8.0$840
07 Jul 2026Tom KowalskiMechanical assembly 8.0$576
06 Jul 2026Luke BrennanPLC & robot programming 7.5$788
06 Jul 2026Ryan WalshMechanical assembly 4.0$288
03 Jul 2026Luke BrennanPLC & robot programming 6.0$630
02 Jul 2026Josh MitchellPLC & robot programming 6.0$600
01 Jul 2026Josh MitchellPLC & robot programming 4.0$400
24 Jun 2026Ben NguyenMachining & fit-up 2.0$148
23 Jun 2026Ben NguyenMachining & fit-up 7.5$555
22 Jun 2026Ben NguyenMachining & fit-up 7.5$555
19 Jun 2026Ben NguyenMachining & fit-up 6.0$444
09 Jun 2026Daniel PhamMechanical design 4.0$380
08 Jun 2026Priya RamanMechanical design 7.5$675
05 Jun 2026Priya RamanMechanical design 4.0$360
04 Jun 2026Priya RamanMechanical design 6.0$540
03 Jun 2026Priya RamanMechanical design 8.0$720
02 Jun 2026Daniel PhamMechanical design 8.0$760
01 Jun 2026Priya RamanMechanical design 8.0$720
29 May 2026Priya RamanMechanical design 6.0$540
28 May 2026Daniel PhamMechanical design 7.5$713
27 May 2026Luke BrennanControls design 2.0$210
27 May 2026Priya RamanMechanical design 8.0$720
26 May 2026Luke BrennanControls design 7.5$788
26 May 2026Daniel PhamMechanical design 7.5$713
25 May 2026Josh MitchellControls design 7.5$750
Project
Customer
Cement Australia — Railton
Neil Garrett · Packing Plant Supervisor
Site
Cement Australia — Railton
Robot
FANUC M-410iC (existing)
PM
Sebastian
Quote
Q-26-0048
Customer PO
CEM-PO-4578112
Key dates
Start
25 May 2026
FAT
05 Aug 2026
Ship
12 Aug 2026
Commissioning
26 Aug 2026
Completed
26 Aug 2026
Money
Value
$79,200
Budget cost
$55,919
Parts committed
$8,585
Parts issued
$8,585
Labour to date
$23,884
Forecast cost
$55,919
Forecast margin
$23,281 · 29.4%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0048 won — project TA-26-024 opened.
19 May, 10:40am · Aiden Clarke