TA-26-034

Design On track

Reel handling — core bung inserter & core trimmer cell, PM6 · Opal Australian Paper · Reel handling — core bung & trimmer

Value
$538,000
budget cost $379k
Cost to date
$23,965
$0 parts · $24k labour
Forecast margin
28.9%
$155,293
Claimed
30%
$161,400 of $538,000
FAT
20 Jan
in 106 days
Parts short
3
3 not on order
Bill of materials
14 lines · $155,409 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CX5130-0125 Beckhoff CX5130 embedded PC (TwinCAT)
Drives & controls · 4 ea free
1 — 1 — $2,480.00 $2,480
ENC-600-SS Control enclosure 600 × 600, stainless
Electrical · 2 ea free
1 — 1 — $920.00 $920
IRB660-250 ABB IRB 660 palletising robot, 250 kg / 3.15 m
Robots · 0 ea free
1 — — 1 $118,600.00 $118,600
C4P-SA15030A SICK deTec4 safety light curtain 1500 mm
Sensors & safety · 4 pair free
2 — 2 — $2,140.00 $4,280
INSPECTORP621 SICK InspectorP621 vision sensor
Sensors & safety · 0 ea free
1 — — 1 $3,890.00 $3,890
PNOZ-MB0 Pilz PNOZmulti 2 safety relay base unit
Sensors & safety · 4 ea free
1 — 1 — $1,180.00 $1,180
XG-DOOR-SL Axelent sliding door kit with interlock
Sensors & safety · 2 ea free
1 — 1 — $1,450.00 $1,450
XG-PANEL-2200 Axelent X-Guard mesh panel 2200 × 1500
Sensors & safety · 36 ea free
16 — 16 — $168.00 $2,688
XG-POST-2200 Axelent X-Guard post 2200
Sensors & safety · 36 ea free
14 — 14 — $64.00 $896
TRK-CBI-HD Core bung inserter head — pneumatic
Trak products · 2 ea free
1 — 1 — $7,400.00 $7,400
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
1 — — 1 $1,380.00 $1,380
TRK-CUT-QC Quick-change core cutter head
Trak products · 4 ea free
2 — 2 — $2,150.00 $4,300
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
1 — 1 — $145.00 $145
SIDECH-2BH19 Side channel blower 2BH1 9.5 kW
Vacuum · 1 ea free
1 — 1 — $5,800.00 $5,800
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $161,40030% of $538,000
Deposit 30%
INV-10457
$161,400 ex GST · $177,540 inc
Awaiting paymentXero synced
FAT 40%
$215,200
not raised
Commissioning 30%
$161,400
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 14 Sep 2026 09 Oct 2026 20 Priya Raman
Procurement Procurement 02 Oct 2026 22 Oct 2026 15 Jess Taylor
Fabrication Excelfab — laser, fold & weld 15 Oct 2026 30 Oct 2026 12 Ben Nguyen
Assembly Assembly bay 1 21 Dec 2026 19 Jan 2027 22 Ryan Walsh
Controls Controls & robot programming 01 Jan 2027 21 Jan 2027 15 Luke Brennan
FAT FAT cell 20 Jan 2027 22 Jan 2027 3 Matt O'Connor
Commissioning Site crew 17 Feb 2027 26 Feb 2027 8 Steve Hargreaves
Time booked
254.0 h · $23,965 at cost rates
Priya Raman106.5 h · $9,585
Daniel Pham100.0 h · $9,500
Luke Brennan26.0 h · $2,730
Josh Mitchell21.5 h · $2,150
DateWhoTaskHoursCost
06 Oct 2026Daniel PhamMechanical design 3.5$333
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Priya RamanMechanical design 7.5$675
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Daniel PhamMechanical design 8.0$760
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Priya RamanMechanical design 4.0$360
05 Oct 2026Priya RamanMechanical design 8.0$720
02 Oct 2026Priya RamanMechanical design 8.0$720
01 Oct 2026Priya RamanMechanical design 4.0$360
30 Sep 2026Priya RamanMechanical design 4.0$360
29 Sep 2026Daniel PhamMechanical design 4.0$380
28 Sep 2026Daniel PhamMechanical design 8.0$760
25 Sep 2026Josh MitchellControls design 2.5$250
25 Sep 2026Priya RamanMechanical design 4.0$360
24 Sep 2026Josh MitchellControls design 7.5$750
24 Sep 2026Priya RamanMechanical design 8.0$720
23 Sep 2026Luke BrennanControls design 4.0$420
23 Sep 2026Priya RamanMechanical design 7.5$675
22 Sep 2026Luke BrennanControls design 4.0$420
22 Sep 2026Daniel PhamMechanical design 6.0$570
21 Sep 2026Luke BrennanControls design 6.0$630
21 Sep 2026Priya RamanMechanical design 4.0$360
18 Sep 2026Luke BrennanControls design 6.0$630
18 Sep 2026Daniel PhamMechanical design 6.0$570
17 Sep 2026Josh MitchellControls design 7.5$750
17 Sep 2026Priya RamanMechanical design 7.5$675
16 Sep 2026Josh MitchellControls design 4.0$400
16 Sep 2026Daniel PhamMechanical design 7.5$713
15 Sep 2026Luke BrennanControls design 6.0$630
15 Sep 2026Priya RamanMechanical design 4.0$360
14 Sep 2026Daniel PhamMechanical design 8.0$760
Project
Customer
Opal Australian Paper
Graham Pike · Mill Engineering Manager
Site
Opal Australian Paper — Maryvale
Robot
ABB IRB 660
PM
Sebastian
Quote
Q-26-0052
Customer PO
OPA-PO-4519637
Key dates
Start
14 Sep 2026
FAT
20 Jan 2027
Ship
27 Jan 2027
Commissioning
17 Feb 2027
Money
Value
$538,000
Budget cost
$378,944
Parts committed
$155,409
Parts issued
$0
Labour to date
$23,965
Forecast cost
$382,707
Forecast margin
$155,293 · 28.9%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Activity
PM6 kick-off at Maryvale.
15 Sep, 12:35pm · Craig Kirkpatrick
Quote Q-26-0052 won — project TA-26-034 opened.
9 Sep, 10:33am · Craig Kirkpatrick