Projects / TA-26-037
TA-26-037
Assembly At riskFork palletising gripper — 20 kg flour bags · Scott Automation & Robotics · Fork palletising
Value
$78,500
budget cost $60k
Cost to date
$25,134
$8k parts · $17k labour
Forecast margin
24.0%
$18,840
Claimed
30%
$23,550 of $78,500
FAT
14 Oct
in 8 days
Parts short
0
BOM covered
Bill of materials
10 lines · $8,585 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| CMP71S-KH4 | SEW CMP71S synchronous servomotor Drives & controls · 1 ea free | 1 | 1 | — | — | $2,120.00 | $2,120 | |
| M12-5P-5M | M12 5-pin cable, 5 m, PUR Electrical · 72 ea free | 6 | 5 | 1 | — | $24.00 | $144 | |
| SHCS-M10-30 | Socket head cap screw M10 × 30, 12.9 (box 50) Fasteners · 15 box free | 1 | 1 | — | — | $38.00 | $38 | |
| DSBC-50-200-PPVA | Festo DSBC standard cylinder Ø50 × 200 Pneumatics · 10 ea free | 2 | 2 | — | — | $268.00 | $536 | |
| AL-PROF-4545 | Aluminium profile 45 × 45, per metre Raw material · 108 m free | 10 | 8 | 2 | — | $21.00 | $210 | |
| AL6061-PL20 | Aluminium plate 6061-T6, 20 mm, 2400 × 1200 Raw material · 4 sheet free | 1 | 1 | — | — | $1,260.00 | $1,260 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 4 | 4 | — | — | $58.00 | $232 | |
| TRK-CSS-L | Compliance shock sensor — large (≤300 kg tooling) Trak products · 0 ea free | 1 | 1 | — | — | $1,380.00 | $1,380 | |
| TRK-FRK-CF11 | Carbon fibre flat fork tine — 1100 mm Trak products · 13 ea free | 6 | 5 | 1 | — | $420.00 | $2,520 | |
| TRK-MP-FAN | Sensor mounting plate — FANUC flange Trak products · 8 ea free | 1 | 1 | — | — | $145.00 | $145 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $23,55030% of $78,500
Deposit 30%
INV-10460
$23,550 ex GST · $25,905 inc
OverdueXero synced
FAT 40%
$31,400
not raised
Commissioning 30%
$23,550
not raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 27 Jul 2026 | 11 Aug 2026 | 12 | Daniel Pham | |
| Procurement | Procurement | 06 Aug 2026 | 19 Aug 2026 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 14 Aug 2026 | 25 Aug 2026 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 28 Sep 2026 | 13 Oct 2026 | 12 | Ryan Walsh | |
| Controls | Controls & robot programming | 05 Oct 2026 | 14 Oct 2026 | 8 | Josh Mitchell | |
| FAT | FAT cell | 14 Oct 2026 | 15 Oct 2026 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 28 Oct 2026 | 30 Oct 2026 | 3 | Steve Hargreaves |
Time booked
193.5 h · $17,035 at cost rates
Daniel Pham47.0 h · $4,465
Priya Raman37.0 h · $3,330
Josh Mitchell33.0 h · $3,300
Tom Kowalski26.5 h · $1,908
Ben Nguyen26.0 h · $1,924
Ryan Walsh12.5 h · $900
Luke Brennan11.5 h · $1,208
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 15 Sep 2026 | Ryan Walsh | Mechanical assembly | 4.5 | $324 | |
| 14 Sep 2026 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 11 Sep 2026 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 10 Sep 2026 | Josh Mitchell | PLC & robot programming | 4.0 | $400 | |
| 10 Sep 2026 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 09 Sep 2026 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 09 Sep 2026 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 08 Sep 2026 | Josh Mitchell | PLC & robot programming | 7.5 | $750 | |
| 08 Sep 2026 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 07 Sep 2026 | Josh Mitchell | PLC & robot programming | 6.0 | $600 | |
| 07 Sep 2026 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 27 Aug 2026 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 26 Aug 2026 | Ben Nguyen | Machining & fit-up | 8.0 | $592 | |
| 25 Aug 2026 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 24 Aug 2026 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 13 Aug 2026 | Daniel Pham | Mechanical design | 1.5 | $143 | |
| 12 Aug 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 11 Aug 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 10 Aug 2026 | Daniel Pham | Mechanical design | 6.0 | $570 | |
| 07 Aug 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 06 Aug 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 05 Aug 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 04 Aug 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 03 Aug 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 31 Jul 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 30 Jul 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 29 Jul 2026 | Luke Brennan | Controls design | 4.0 | $420 | |
| 29 Jul 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 28 Jul 2026 | Josh Mitchell | Controls design | 7.5 | $750 | |
| 28 Jul 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 27 Jul 2026 | Josh Mitchell | Controls design | 8.0 | $800 |
Project
- Customer
- Scott Automation & RoboticsMitchell Hayes · Project Manager
- Site
- Scott Automation & Robotics — Rocklea
- Robot
- ABB IRB 460 (existing)
- PM
- Sebastian
- Quote
- Q-26-0055
- Customer PO
- SCO-PO-4531558
Key dates
- Start
- 27 Jul 2026
- FAT
- 14 Oct 2026
- Ship
- 21 Oct 2026
- Commissioning
- 28 Oct 2026
Money
- Value
- $78,500
- Budget cost
- $59,660
- Parts committed
- $8,585
- Parts issued
- $8,099
- Labour to date
- $17,035
- Forecast cost
- $59,660
- Forecast margin
- $18,840 · 24.0%
Notes
SEW servo for fork drive held at supplier — revised ETA 9 Oct. Assembly continuing around it.
Purchase orders
All POsCalendar
CalendarActivity
Quote Q-26-0055 won — project TA-26-037 opened.
17 Jul, 10:11am · Craig Kirkpatrick