TA-26-038 · Orica — Kooragang Island Demo Bag palletising cell — 25 kg AN bags (fork gripper)
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-038

TA-26-038

Procurement On track

Bag palletising cell — 25 kg AN bags (fork gripper) · Orica — Kooragang Island · Fork palletising

Value
$356,000
budget cost $253k
Cost to date
$40,893
$0 parts · $41k labour
Forecast margin
29.0%
$103,277
Claimed
30%
$106,800 of $356,000
FAT
9 Dec
in 64 days
Parts short
0
BOM covered
Bill of materials
10 lines · $8,585 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CMP71S-KH4 SEW CMP71S synchronous servomotor
Drives & controls · 1 ea free
1 — 1 — $2,120.00 $2,120
M12-5P-5M M12 5-pin cable, 5 m, PUR
Electrical · 72 ea free
6 — 6 — $24.00 $144
SHCS-M10-30 Socket head cap screw M10 × 30, 12.9 (box 50)
Fasteners · 15 box free
1 — 1 — $38.00 $38
DSBC-50-200-PPVA Festo DSBC standard cylinder Ø50 × 200
Pneumatics · 10 ea free
2 — 2 — $268.00 $536
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
10 — 10 — $21.00 $210
AL6061-PL20 Aluminium plate 6061-T6, 20 mm, 2400 × 1200
Raw material · 4 sheet free
1 — 1 — $1,260.00 $1,260
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
4 — 4 — $58.00 $232
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
1 — 1 — $1,380.00 $1,380
TRK-FRK-CF11 Carbon fibre flat fork tine — 1100 mm
Trak products · 13 ea free
6 — 6 — $420.00 $2,520
TRK-MP-FAN Sensor mounting plate — FANUC flange
Trak products · 8 ea free
1 — 1 — $145.00 $145
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $106,80030% of $356,000
Deposit 30%
INV-10461
$106,800 ex GST · $117,480 inc
Awaiting paymentXero synced
FAT 40%
$142,400
not raised
Commissioning 30%
$106,800
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 24 Aug 2026 08 Sep 2026 12 Daniel Pham
Procurement Procurement 03 Sep 2026 16 Sep 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 11 Sep 2026 22 Sep 2026 8 Ben Nguyen
Assembly Gripper assembly bench 23 Nov 2026 08 Dec 2026 12 Ryan Walsh
Controls Controls & robot programming 30 Nov 2026 09 Dec 2026 8 Luke Brennan
FAT FAT cell 09 Dec 2026 10 Dec 2026 2 Matt O'Connor
Commissioning Site crew 20 Jan 2027 22 Jan 2027 3 Steve Hargreaves
Time booked
432.0 h · $40,893 at cost rates
Daniel Pham183.5 h · $17,433
Priya Raman167.5 h · $15,075
Luke Brennan57.0 h · $5,985
Josh Mitchell24.0 h · $2,400
DateWhoTaskHoursCost
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Daniel PhamMechanical design 8.0$760
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Priya RamanMechanical design 8.0$720
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Priya RamanMechanical design 8.0$720
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Priya RamanMechanical design 8.0$720
06 Oct 2026Priya RamanMechanical design 7.5$675
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Priya RamanMechanical design 7.5$675
05 Oct 2026Daniel PhamMechanical design 7.5$713
02 Oct 2026Priya RamanMechanical design 7.5$675
01 Oct 2026Priya RamanMechanical design 4.0$360
30 Sep 2026Daniel PhamMechanical design 7.5$713
29 Sep 2026Daniel PhamMechanical design 6.0$570
28 Sep 2026Daniel PhamMechanical design 7.5$713
25 Sep 2026Priya RamanMechanical design 8.0$720
24 Sep 2026Priya RamanMechanical design 6.0$540
23 Sep 2026Daniel PhamMechanical design 8.0$760
22 Sep 2026Priya RamanMechanical design 7.5$675
21 Sep 2026Priya RamanMechanical design 6.0$540
18 Sep 2026Priya RamanMechanical design 8.0$720
17 Sep 2026Daniel PhamMechanical design 6.0$570
16 Sep 2026Priya RamanMechanical design 4.0$360
15 Sep 2026Luke BrennanControls design 0.5$53
15 Sep 2026Priya RamanMechanical design 8.0$720
14 Sep 2026Luke BrennanControls design 7.5$788
14 Sep 2026Priya RamanMechanical design 4.0$360
11 Sep 2026Luke BrennanControls design 8.0$840
11 Sep 2026Daniel PhamMechanical design 6.0$570
10 Sep 2026Luke BrennanControls design 6.0$630
10 Sep 2026Priya RamanMechanical design 7.5$675
09 Sep 2026Luke BrennanControls design 7.5$788
09 Sep 2026Priya RamanMechanical design 6.0$540
08 Sep 2026Josh MitchellControls design 6.0$600
08 Sep 2026Priya RamanMechanical design 4.0$360
07 Sep 2026Luke BrennanControls design 4.0$420
07 Sep 2026Daniel PhamMechanical design 7.5$713
04 Sep 2026Josh MitchellControls design 4.0$400
04 Sep 2026Daniel PhamMechanical design 8.0$760
03 Sep 2026Josh MitchellControls design 6.0$600
03 Sep 2026Daniel PhamMechanical design 4.0$380
Project
Customer
Orica — Kooragang Island
David Achterberg · Bagging Plant Engineer
Site
Orica — Kooragang
Robot
ABB IRB 460 (existing)
PM
Sebastian
Quote
Q-26-0056
Customer PO
ORI-PO-4510690
Key dates
Start
24 Aug 2026
FAT
09 Dec 2026
Ship
16 Dec 2026
Commissioning
20 Jan 2027
Money
Value
$356,000
Budget cost
$252,723
Parts committed
$8,585
Parts issued
$0
Labour to date
$40,893
Forecast cost
$252,723
Forecast margin
$103,277 · 29.0%
Purchase orders
All POs
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0056 won — project TA-26-038 opened.
17 Aug, 10:29am · Craig Kirkpatrick