Projects / TA-26-040
TA-26-040
Dispatch On trackReel handling — core bung inserter, Tissue Machine 2 · Kimberly-Clark Australia · Reel handling — core bung & trimmer
Value
$264,000
budget cost $200k
Cost to date
$172,776
$155k parts · $17k labour
Forecast margin
24.4%
$64,369
Claimed
70%
$184,800 of $264,000
FAT
30 Sep
signed off
Parts short
0
BOM covered
Bill of materials
14 lines · $155,409 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| CX5130-0125 | Beckhoff CX5130 embedded PC (TwinCAT) Drives & controls · 4 ea free | 1 | 1 | — | — | $2,480.00 | $2,480 | |
| ENC-600-SS | Control enclosure 600 × 600, stainless Electrical · 2 ea free | 1 | 1 | — | — | $920.00 | $920 | |
| IRB660-250 | ABB IRB 660 palletising robot, 250 kg / 3.15 m Robots · 0 ea free | 1 | 1 | — | — | $118,600.00 | $118,600 | |
| C4P-SA15030A | SICK deTec4 safety light curtain 1500 mm Sensors & safety · 4 pair free | 2 | 2 | — | — | $2,140.00 | $4,280 | |
| INSPECTORP621 | SICK InspectorP621 vision sensor Sensors & safety · 0 ea free | 1 | 1 | — | — | $3,890.00 | $3,890 | |
| PNOZ-MB0 | Pilz PNOZmulti 2 safety relay base unit Sensors & safety · 4 ea free | 1 | 1 | — | — | $1,180.00 | $1,180 | |
| XG-DOOR-SL | Axelent sliding door kit with interlock Sensors & safety · 2 ea free | 1 | 1 | — | — | $1,450.00 | $1,450 | |
| XG-PANEL-2200 | Axelent X-Guard mesh panel 2200 × 1500 Sensors & safety · 36 ea free | 16 | 16 | — | — | $168.00 | $2,688 | |
| XG-POST-2200 | Axelent X-Guard post 2200 Sensors & safety · 36 ea free | 14 | 14 | — | — | $64.00 | $896 | |
| TRK-CBI-HD | Core bung inserter head — pneumatic Trak products · 2 ea free | 1 | 1 | — | — | $7,400.00 | $7,400 | |
| TRK-CSS-L | Compliance shock sensor — large (≤300 kg tooling) Trak products · 0 ea free | 1 | 1 | — | — | $1,380.00 | $1,380 | |
| TRK-CUT-QC | Quick-change core cutter head Trak products · 4 ea free | 2 | 2 | — | — | $2,150.00 | $4,300 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 1 | 1 | — | — | $145.00 | $145 | |
| SIDECH-2BH19 | Side channel blower 2BH1 9.5 kW Vacuum · 1 ea free | 1 | 1 | — | — | $5,800.00 | $5,800 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $184,80070% of $264,000
Deposit 30%
INV-10464
$79,200 ex GST · $87,120 inc
PaidXero synced
FAT 40%
INV-10465
$105,600 ex GST · $116,160 inc
Awaiting paymentXero synced
Commissioning 30%
$79,200
not raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 11 May 2026 | 05 Jun 2026 | 20 | Daniel Pham | |
| Procurement | Procurement | 29 May 2026 | 18 Jun 2026 | 15 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 11 Jun 2026 | 26 Jun 2026 | 12 | Ben Nguyen | |
| Assembly | Assembly bay 2 | 31 Aug 2026 | 29 Sep 2026 | 22 | Tom Kowalski | |
| Controls | Controls & robot programming | 11 Sep 2026 | 01 Oct 2026 | 15 | Luke Brennan | |
| FAT | FAT cell | 30 Sep 2026 | 02 Oct 2026 | 3 | Matt O'Connor | |
| Commissioning | Site crew | 27 Oct 2026 | 05 Nov 2026 | 8 | Steve Hargreaves |
Time booked
197.5 h · $17,367 at cost rates
Priya Raman49.0 h · $4,410
Ryan Walsh45.5 h · $3,276
Luke Brennan33.0 h · $3,465
Josh Mitchell29.5 h · $2,950
Ben Nguyen19.5 h · $1,443
Daniel Pham13.5 h · $1,283
Tom Kowalski7.5 h · $540
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 06 Jul 2026 | Luke Brennan | FAT | 4.5 | $473 | |
| 03 Jul 2026 | Luke Brennan | FAT | 6.0 | $630 | |
| 02 Jul 2026 | Luke Brennan | FAT | 4.0 | $420 | |
| 02 Jul 2026 | Ryan Walsh | Mechanical assembly | 3.0 | $216 | |
| 01 Jul 2026 | Ryan Walsh | Mechanical assembly | 7.5 | $540 | |
| 30 Jun 2026 | Ryan Walsh | Mechanical assembly | 7.5 | $540 | |
| 29 Jun 2026 | Josh Mitchell | PLC & robot programming | 5.5 | $550 | |
| 29 Jun 2026 | Ryan Walsh | Mechanical assembly | 7.5 | $540 | |
| 26 Jun 2026 | Josh Mitchell | PLC & robot programming | 8.0 | $800 | |
| 26 Jun 2026 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 25 Jun 2026 | Josh Mitchell | PLC & robot programming | 6.0 | $600 | |
| 25 Jun 2026 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 24 Jun 2026 | Luke Brennan | PLC & robot programming | 4.0 | $420 | |
| 24 Jun 2026 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 23 Jun 2026 | Josh Mitchell | PLC & robot programming | 6.0 | $600 | |
| 23 Jun 2026 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 22 Jun 2026 | Luke Brennan | PLC & robot programming | 4.0 | $420 | |
| 22 Jun 2026 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 10 Jun 2026 | Ben Nguyen | Machining & fit-up | 0.5 | $37 | |
| 09 Jun 2026 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 08 Jun 2026 | Ben Nguyen | Machining & fit-up | 7.5 | $555 | |
| 05 Jun 2026 | Ben Nguyen | Machining & fit-up | 7.5 | $555 | |
| 26 May 2026 | Priya Raman | Mechanical design | 0.5 | $45 | |
| 25 May 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 22 May 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 21 May 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 20 May 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 19 May 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 18 May 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 15 May 2026 | Luke Brennan | Controls design | 4.5 | $473 | |
| 15 May 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 14 May 2026 | Luke Brennan | Controls design | 6.0 | $630 | |
| 14 May 2026 | Daniel Pham | Mechanical design | 6.0 | $570 | |
| 13 May 2026 | Josh Mitchell | Controls design | 4.0 | $400 | |
| 13 May 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 12 May 2026 | Priya Raman | Mechanical design | 6.0 | $540 |
Project
- Customer
- Kimberly-Clark AustraliaPaul Richter · Engineering Manager — Millicent Mill
- Site
- Kimberly-Clark Australia — Millicent
- Robot
- ABB IRB 660
- PM
- Sebastian
- Quote
- Q-26-0058
- Customer PO
- KCA-PO-4569249
Key dates
- Start
- 11 May 2026
- FAT
- 30 Sep 2026
- Ship
- 09 Oct 2026
- Commissioning
- 27 Oct 2026
Money
- Value
- $264,000
- Budget cost
- $199,631
- Parts committed
- $155,409
- Parts issued
- $155,409
- Labour to date
- $17,367
- Forecast cost
- $199,631
- Forecast margin
- $64,369 · 24.4%
Purchase orders
All POsCalendar
CalendarActivity
FAT passed — TA-26-040 core bung inserter. Ships 9 Oct.
30 Sep, 4:55pm · Craig Kirkpatrick
Quote Q-26-0058 won — project TA-26-040 opened.
6 May, 10:02am · Craig Kirkpatrick