Projects / TA-25-026
TA-25-026
Complete On trackSide clamp servo grippers ×3 — for Fibre King palletisers · Fibre King · Side clamp servo palletising
Value
$236,000
budget cost $176k
Cost to date
$109,068
$30k parts · $79k labour
Forecast margin
25.2%
$59,534
Claimed
100%
$236,000 of $236,000
FAT
26 Nov
signed off
Parts short
0
BOM covered
Bill of materials
13 lines · $29,976 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| AM8042-1F20 | Beckhoff AM8042 servo motor, 1.4 Nm Drives & controls · 1 ea free | 3 | 3 | — | — | $1,380.00 | $4,140 | |
| M12-5P-5M | M12 5-pin cable, 5 m, PUR Electrical · 72 ea free | 18 | 18 | — | — | $24.00 | $432 | |
| SHCS-M8-25 | Socket head cap screw M8 × 25, 12.9 (box 100) Fasteners · 18 box free | 3 | 3 | — | — | $34.00 | $102 | |
| ADN-32-40-A-P-A | Festo ADN compact cylinder Ø32 × 40 Pneumatics · 22 ea free | 6 | 6 | — | — | $118.00 | $708 | |
| VTUG-10-8M | Festo VTUG valve terminal, 8 stations, IO-Link Pneumatics · 5 ea free | 3 | 3 | — | — | $1,290.00 | $3,870 | |
| AL-PROF-4545 | Aluminium profile 45 × 45, per metre Raw material · 108 m free | 18 | 18 | — | — | $21.00 | $378 | |
| AL6061-PL10 | Aluminium plate 6061-T6, 10 mm, 2400 × 1200 Raw material · 7 sheet free | 3 | 3 | — | — | $640.00 | $1,920 | |
| CF-PLATE-6 | Carbon fibre plate 6 mm, 1000 × 600 Raw material · 3 sheet free | 3 | 3 | — | — | $545.00 | $1,635 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 12 | 12 | — | — | $58.00 | $696 | |
| TRK-CSS-M | Compliance shock sensor — medium (≤150 kg tooling) Trak products · 10 ea free | 3 | 3 | — | — | $1,020.00 | $3,060 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 3 | 3 | — | — | $145.00 | $435 | |
| TRK-SP-SCS | Side clamp plate — carbon fibre, 1250 mm Trak products · 2 ea free | 6 | 6 | — | — | $680.00 | $4,080 | |
| GEP2016IL-00-B | Zimmer GEP2016IL electric parallel gripper, IO-Link Zimmer components · 7 ea free | 6 | 6 | — | — | $1,420.00 | $8,520 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 01 Sep 2025 | 16 Sep 2025 | 12 | Daniel Pham | |
| Procurement | Procurement | 11 Sep 2025 | 24 Sep 2025 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 19 Sep 2025 | 30 Sep 2025 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 10 Nov 2025 | 25 Nov 2025 | 12 | Ryan Walsh | |
| Controls | Controls & robot programming | 17 Nov 2025 | 26 Nov 2025 | 8 | Josh Mitchell | |
| FAT | FAT cell | 26 Nov 2025 | 27 Nov 2025 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 10 Dec 2025 | 12 Dec 2025 | 3 | Steve Hargreaves |
Time booked
893.0 h · $79,092 at cost rates
Daniel Pham160.5 h · $15,248
Josh Mitchell142.5 h · $14,250
Luke Brennan125.0 h · $13,125
Tom Kowalski109.5 h · $7,884
Ryan Walsh99.5 h · $7,164
Priya Raman86.5 h · $7,785
Ben Nguyen76.0 h · $5,624
Steve Hargreaves66.5 h · $5,852
Matt O'Connor27.0 h · $2,160
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 11 Dec 2025 | Luke Brennan | Site commissioning | 6.0 | $630 | |
| 10 Dec 2025 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 09 Dec 2025 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 08 Dec 2025 | Steve Hargreaves | Site commissioning | 8.0 | $704 | |
| 05 Dec 2025 | Steve Hargreaves | Site commissioning | 7.5 | $660 | |
| 04 Dec 2025 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 03 Dec 2025 | Luke Brennan | Site commissioning | 6.0 | $630 | |
| 02 Dec 2025 | Steve Hargreaves | Site commissioning | 7.5 | $660 | |
| 01 Dec 2025 | Luke Brennan | Site commissioning | 8.0 | $840 | |
| 28 Nov 2025 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 27 Nov 2025 | Luke Brennan | Site commissioning | 7.5 | $788 | |
| 26 Nov 2025 | Steve Hargreaves | Site commissioning | 8.0 | $704 | |
| 25 Nov 2025 | Steve Hargreaves | Site commissioning | 8.0 | $704 | |
| 24 Nov 2025 | Luke Brennan | Site commissioning | 8.0 | $840 | |
| 24 Nov 2025 | Ryan Walsh | Mechanical assembly | 0.5 | $36 | |
| 21 Nov 2025 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 21 Nov 2025 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 20 Nov 2025 | Steve Hargreaves | Site commissioning | 8.0 | $704 | |
| 20 Nov 2025 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 19 Nov 2025 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 19 Nov 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 | |
| 18 Nov 2025 | Steve Hargreaves | Site commissioning | 7.5 | $660 | |
| 18 Nov 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 | |
| 17 Nov 2025 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 14 Nov 2025 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 13 Nov 2025 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 12 Nov 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 | |
| 11 Nov 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 10 Nov 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 07 Nov 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 | |
| 06 Nov 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 05 Nov 2025 | Matt O'Connor | FAT | 3.5 | $280 | |
| 05 Nov 2025 | Luke Brennan | PLC & robot programming | 2.0 | $210 | |
| 05 Nov 2025 | Ryan Walsh | Mechanical assembly | 7.5 | $540 | |
| 04 Nov 2025 | Luke Brennan | FAT | 8.0 | $840 | |
| 04 Nov 2025 | Josh Mitchell | PLC & robot programming | 4.0 | $400 | |
| 04 Nov 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 03 Nov 2025 | Matt O'Connor | FAT | 8.0 | $640 | |
| 03 Nov 2025 | Josh Mitchell | PLC & robot programming | 7.5 | $750 | |
| 03 Nov 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 | |
| 31 Oct 2025 | Matt O'Connor | FAT | 8.0 | $640 | |
| 31 Oct 2025 | Josh Mitchell | PLC & robot programming | 7.5 | $750 | |
| 31 Oct 2025 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 30 Oct 2025 | Luke Brennan | FAT | 6.0 | $630 | |
| 30 Oct 2025 | Luke Brennan | PLC & robot programming | 4.0 | $420 | |
| 30 Oct 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 29 Oct 2025 | Luke Brennan | FAT | 8.0 | $840 | |
| 29 Oct 2025 | Josh Mitchell | PLC & robot programming | 8.0 | $800 | |
| 29 Oct 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 | |
| 28 Oct 2025 | Luke Brennan | FAT | 4.0 | $420 | |
| 28 Oct 2025 | Josh Mitchell | PLC & robot programming | 8.0 | $800 | |
| 28 Oct 2025 | Ryan Walsh | Mechanical assembly | 8.0 | $576 | |
| 27 Oct 2025 | Matt O'Connor | FAT | 7.5 | $600 | |
| 27 Oct 2025 | Josh Mitchell | PLC & robot programming | 8.0 | $800 | |
| 27 Oct 2025 | Ryan Walsh | Mechanical assembly | 8.0 | $576 | |
| 24 Oct 2025 | Luke Brennan | FAT | 4.0 | $420 | |
| 24 Oct 2025 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 24 Oct 2025 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 23 Oct 2025 | Luke Brennan | PLC & robot programming | 4.0 | $420 | |
| 23 Oct 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 |
Project
- Customer
- Fibre KingGreg Hollis · Engineering Manager
- Site
- Fibre King — Dandenong South
- Robot
- FANUC M-410iC (existing)
- PM
- Sebastian
- Quote
- Q-25-0063
- Customer PO
- FIB-PO-4507480
Key dates
- Start
- 01 Sep 2025
- FAT
- 26 Nov 2025
- Ship
- 03 Dec 2025
- Commissioning
- 10 Dec 2025
- Completed
- 10 Dec 2025
Money
- Value
- $236,000
- Budget cost
- $176,466
- Parts committed
- $29,976
- Parts issued
- $29,976
- Labour to date
- $79,092
- Forecast cost
- $176,466
- Forecast margin
- $59,534 · 25.2%
Purchase orders
All POsNo purchase orders for this project.
Calendar
CalendarNothing in the calendar.
Activity
Quote Q-25-0063 won — project TA-25-026 opened.
26 Aug, 10:37am · Craig Kirkpatrick