Projects / TA-26-005
TA-26-005
Complete On trackRobot roller layer palletising gripper · Scott Automation & Robotics · Robot layer palletising
Value
$74,800
budget cost $49k
Cost to date
$33,358
$16k parts · $17k labour
Forecast margin
34.3%
$25,649
Claimed
100%
$74,800 of $74,800
FAT
11 Mar
signed off
Parts short
0
BOM covered
Bill of materials
12 lines · $16,495 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| AM8053-1J20 | Beckhoff AM8053 servo motor, 4.0 Nm Drives & controls · 0 ea free | 2 | 2 | — | — | $2,240.00 | $4,480 | |
| AX5203-0000 | Beckhoff AX5203 2-ch servo drive Drives & controls · 0 ea free | 1 | 1 | — | — | $2,960.00 | $2,960 | |
| E4-1-12-15-0 | igus E4.1 energy chain, per metre Drives & controls · 18 m free | 3 | 3 | — | — | $64.00 | $192 | |
| SHCS-M10-30 | Socket head cap screw M10 × 30, 12.9 (box 50) Fasteners · 15 box free | 2 | 2 | — | — | $38.00 | $76 | |
| DSBC-50-200-PPVA | Festo DSBC standard cylinder Ø50 × 200 Pneumatics · 10 ea free | 4 | 4 | — | — | $268.00 | $1,072 | |
| AL-PROF-4545 | Aluminium profile 45 × 45, per metre Raw material · 108 m free | 14 | 14 | — | — | $21.00 | $294 | |
| AL6061-PL20 | Aluminium plate 6061-T6, 20 mm, 2400 × 1200 Raw material · 4 sheet free | 1 | 1 | — | — | $1,260.00 | $1,260 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 6 | 6 | — | — | $58.00 | $348 | |
| WTB4-3P2161 | SICK WTB4 photoelectric sensor Sensors & safety · 22 ea free | 4 | 4 | — | — | $142.00 | $568 | |
| TRK-CSS-L | Compliance shock sensor — large (≤300 kg tooling) Trak products · 0 ea free | 1 | 1 | — | — | $1,380.00 | $1,380 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 1 | 1 | — | — | $145.00 | $145 | |
| TRK-RLR-CF12 | Carbon fibre roller — 1200 mm (layer gripper) Trak products · 0 ea free | 12 | 12 | — | — | $310.00 | $3,720 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 12 Jan 2026 | 27 Jan 2026 | 12 | Priya Raman | |
| Procurement | Procurement | 22 Jan 2026 | 04 Feb 2026 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 30 Jan 2026 | 10 Feb 2026 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 23 Feb 2026 | 10 Mar 2026 | 12 | Ryan Walsh | |
| Controls | Controls & robot programming | 02 Mar 2026 | 11 Mar 2026 | 8 | Luke Brennan | |
| FAT | FAT cell | 11 Mar 2026 | 12 Mar 2026 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 23 Mar 2026 | 25 Mar 2026 | 3 | Steve Hargreaves |
Time booked
190.0 h · $16,863 at cost rates
Luke Brennan37.0 h · $3,885
Daniel Pham30.5 h · $2,898
Ryan Walsh28.5 h · $2,052
Josh Mitchell24.0 h · $2,400
Priya Raman22.0 h · $1,980
Tom Kowalski16.0 h · $1,152
Ben Nguyen16.0 h · $1,184
Matt O'Connor12.0 h · $960
Steve Hargreaves4.0 h · $352
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 01 Apr 2026 | Luke Brennan | Site commissioning | 7.0 | $735 | |
| 31 Mar 2026 | Luke Brennan | Site commissioning | 6.0 | $630 | |
| 30 Mar 2026 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 27 Mar 2026 | Luke Brennan | Site commissioning | 7.5 | $788 | |
| 06 Mar 2026 | Matt O'Connor | FAT | 6.0 | $480 | |
| 05 Mar 2026 | Matt O'Connor | FAT | 6.0 | $480 | |
| 03 Mar 2026 | Ryan Walsh | Mechanical assembly | 6.5 | $468 | |
| 02 Mar 2026 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 27 Feb 2026 | Josh Mitchell | PLC & robot programming | 1.0 | $100 | |
| 27 Feb 2026 | Ryan Walsh | Mechanical assembly | 8.0 | $576 | |
| 26 Feb 2026 | Josh Mitchell | PLC & robot programming | 4.0 | $400 | |
| 26 Feb 2026 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 25 Feb 2026 | Luke Brennan | PLC & robot programming | 6.0 | $630 | |
| 25 Feb 2026 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 24 Feb 2026 | Luke Brennan | PLC & robot programming | 6.0 | $630 | |
| 24 Feb 2026 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 23 Feb 2026 | Josh Mitchell | PLC & robot programming | 4.0 | $400 | |
| 23 Feb 2026 | Ryan Walsh | Mechanical assembly | 4.0 | $288 | |
| 20 Feb 2026 | Josh Mitchell | PLC & robot programming | 7.5 | $750 | |
| 20 Feb 2026 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 12 Feb 2026 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 11 Feb 2026 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 10 Feb 2026 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 26 Jan 2026 | Daniel Pham | Mechanical design | 2.5 | $238 | |
| 23 Jan 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 22 Jan 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 21 Jan 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 20 Jan 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 19 Jan 2026 | Luke Brennan | Controls design | 0.5 | $53 | |
| 19 Jan 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 16 Jan 2026 | Luke Brennan | Controls design | 4.0 | $420 | |
| 16 Jan 2026 | Daniel Pham | Mechanical design | 6.0 | $570 | |
| 15 Jan 2026 | Josh Mitchell | Controls design | 7.5 | $750 | |
| 15 Jan 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 14 Jan 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 13 Jan 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 12 Jan 2026 | Daniel Pham | Mechanical design | 6.0 | $570 |
Project
- Customer
- Scott Automation & RoboticsMitchell Hayes · Project Manager
- Site
- Scott Automation & Robotics — Rocklea
- Robot
- FANUC M-410iC (existing)
- PM
- Sebastian
- Quote
- Q-26-0042
- Customer PO
- SCO-PO-4569476
Key dates
- Start
- 12 Jan 2026
- FAT
- 11 Mar 2026
- Ship
- 16 Mar 2026
- Commissioning
- 23 Mar 2026
- Completed
- 23 Mar 2026
Money
- Value
- $74,800
- Budget cost
- $49,151
- Parts committed
- $16,495
- Parts issued
- $16,495
- Labour to date
- $16,863
- Forecast cost
- $49,151
- Forecast margin
- $25,649 · 34.3%
Purchase orders
All POsNo purchase orders for this project.
Calendar
CalendarNothing in the calendar.
Activity
Quote Q-26-0042 won — project TA-26-005 opened.
6 Jan, 10:15am · Craig Kirkpatrick