TA-26-017 · Mars Wrigley Australia Demo Side clamp servo palletising gripper — shelf-ready cartons
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-017

TA-26-017

Complete On track

Side clamp servo palletising gripper — shelf-ready cartons · Mars Wrigley Australia · Side clamp servo palletising

Value
$96,500
budget cost $72k
Cost to date
$39,744
$10k parts · $30k labour
Forecast margin
25.0%
$24,130
Claimed
100%
$96,500 of $96,500
FAT
24 Jun
signed off
Parts short
0
BOM covered
Bill of materials
13 lines · $9,992 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
AM8042-1F20 Beckhoff AM8042 servo motor, 1.4 Nm
Drives & controls · 1 ea free
1 1 — — $1,380.00 $1,380
M12-5P-5M M12 5-pin cable, 5 m, PUR
Electrical · 72 ea free
6 6 — — $24.00 $144
SHCS-M8-25 Socket head cap screw M8 × 25, 12.9 (box 100)
Fasteners · 18 box free
1 1 — — $34.00 $34
ADN-32-40-A-P-A Festo ADN compact cylinder Ø32 × 40
Pneumatics · 22 ea free
2 2 — — $118.00 $236
VTUG-10-8M Festo VTUG valve terminal, 8 stations, IO-Link
Pneumatics · 5 ea free
1 1 — — $1,290.00 $1,290
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
6 6 — — $21.00 $126
AL6061-PL10 Aluminium plate 6061-T6, 10 mm, 2400 × 1200
Raw material · 7 sheet free
1 1 — — $640.00 $640
CF-PLATE-6 Carbon fibre plate 6 mm, 1000 × 600
Raw material · 3 sheet free
1 1 — — $545.00 $545
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
4 4 — — $58.00 $232
TRK-CSS-M Compliance shock sensor — medium (≤150 kg tooling)
Trak products · 10 ea free
1 1 — — $1,020.00 $1,020
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
1 1 — — $145.00 $145
TRK-SP-SCS Side clamp plate — carbon fibre, 1250 mm
Trak products · 2 ea free
2 2 — — $680.00 $1,360
GEP2016IL-00-B Zimmer GEP2016IL electric parallel gripper, IO-Link
Zimmer components · 7 ea free
2 2 — — $1,420.00 $2,840
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 13 Apr 2026 28 Apr 2026 12 Priya Raman
Procurement Procurement 23 Apr 2026 06 May 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 01 May 2026 12 May 2026 8 Ben Nguyen
Assembly Gripper assembly bench 08 Jun 2026 23 Jun 2026 12 Tom Kowalski
Controls Controls & robot programming 15 Jun 2026 24 Jun 2026 8 Luke Brennan
FAT FAT cell 24 Jun 2026 25 Jun 2026 2 Matt O'Connor
Commissioning Site crew 14 Jul 2026 16 Jul 2026 3 Steve Hargreaves
Time booked
334.0 h · $29,752 at cost rates
Luke Brennan66.5 h · $6,983
Priya Raman47.5 h · $4,275
Daniel Pham45.0 h · $4,275
Tom Kowalski42.5 h · $3,060
Josh Mitchell41.5 h · $4,150
Ryan Walsh35.5 h · $2,556
Ben Nguyen28.5 h · $2,109
Steve Hargreaves23.0 h · $2,024
Matt O'Connor4.0 h · $320
DateWhoTaskHoursCost
09 Jul 2026Luke BrennanSite commissioning 2.0$210
08 Jul 2026Steve HargreavesSite commissioning 7.5$660
07 Jul 2026Steve HargreavesSite commissioning 8.0$704
06 Jul 2026Steve HargreavesSite commissioning 7.5$660
03 Jul 2026Luke BrennanSite commissioning 6.0$630
02 Jul 2026Luke BrennanSite commissioning 7.5$788
01 Jul 2026Luke BrennanSite commissioning 4.0$420
05 Jun 2026Luke BrennanFAT 5.5$578
05 Jun 2026Tom KowalskiMechanical assembly 0.5$36
04 Jun 2026Luke BrennanFAT 6.0$630
04 Jun 2026Tom KowalskiMechanical assembly 8.0$576
03 Jun 2026Matt O'ConnorFAT 4.0$320
03 Jun 2026Ryan WalshMechanical assembly 7.5$540
02 Jun 2026Luke BrennanFAT 6.0$630
02 Jun 2026Josh MitchellPLC & robot programming 3.5$350
02 Jun 2026Tom KowalskiMechanical assembly 8.0$576
01 Jun 2026Luke BrennanPLC & robot programming 8.0$840
01 Jun 2026Ryan WalshMechanical assembly 4.0$288
29 May 2026Josh MitchellPLC & robot programming 8.0$800
29 May 2026Tom KowalskiMechanical assembly 4.0$288
28 May 2026Luke BrennanPLC & robot programming 4.0$420
28 May 2026Ryan WalshMechanical assembly 8.0$576
27 May 2026Josh MitchellPLC & robot programming 6.0$600
27 May 2026Ryan WalshMechanical assembly 8.0$576
26 May 2026Luke BrennanPLC & robot programming 8.0$840
26 May 2026Tom KowalskiMechanical assembly 8.0$576
25 May 2026Luke BrennanPLC & robot programming 4.0$420
25 May 2026Tom KowalskiMechanical assembly 8.0$576
22 May 2026Josh MitchellPLC & robot programming 4.0$400
22 May 2026Ryan WalshMechanical assembly 8.0$576
21 May 2026Josh MitchellPLC & robot programming 4.0$400
21 May 2026Tom KowalskiMechanical assembly 6.0$432
18 May 2026Ben NguyenMachining & fit-up 5.0$370
15 May 2026Ben NguyenMachining & fit-up 7.5$555
14 May 2026Ben NguyenMachining & fit-up 4.0$296
13 May 2026Ben NguyenMachining & fit-up 8.0$592
12 May 2026Ben NguyenMachining & fit-up 4.0$296
04 May 2026Daniel PhamMechanical design 5.0$475
01 May 2026Daniel PhamMechanical design 6.0$570
30 Apr 2026Priya RamanMechanical design 6.0$540
29 Apr 2026Daniel PhamMechanical design 6.0$570
28 Apr 2026Priya RamanMechanical design 6.0$540
27 Apr 2026Priya RamanMechanical design 6.0$540
24 Apr 2026Priya RamanMechanical design 8.0$720
23 Apr 2026Daniel PhamMechanical design 8.0$760
22 Apr 2026Priya RamanMechanical design 4.0$360
21 Apr 2026Daniel PhamMechanical design 4.0$380
20 Apr 2026Luke BrennanControls design 5.5$578
20 Apr 2026Priya RamanMechanical design 6.0$540
17 Apr 2026Josh MitchellControls design 4.0$400
17 Apr 2026Daniel PhamMechanical design 8.0$760
16 Apr 2026Josh MitchellControls design 8.0$800
16 Apr 2026Priya RamanMechanical design 7.5$675
15 Apr 2026Josh MitchellControls design 4.0$400
15 Apr 2026Priya RamanMechanical design 4.0$360
14 Apr 2026Daniel PhamMechanical design 4.0$380
13 Apr 2026Daniel PhamMechanical design 4.0$380
Project
Customer
Mars Wrigley Australia
Laura Bennett · Technical Project Manager
Site
Mars Wrigley Australia — Ballarat
Robot
FANUC M-410iC (existing)
PM
Sebastian
Quote
Q-26-0046
Customer PO
MAR-PO-4591007
Key dates
Start
13 Apr 2026
FAT
24 Jun 2026
Ship
01 Jul 2026
Commissioning
14 Jul 2026
Completed
14 Jul 2026
Money
Value
$96,500
Budget cost
$72,370
Parts committed
$9,992
Parts issued
$9,992
Labour to date
$29,752
Forecast cost
$72,370
Forecast margin
$24,130 · 25.0%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0046 won — project TA-26-017 opened.
6 Apr, 10:17am · Craig Kirkpatrick