Trak
Trak
TA-26-020 · Fonterra Australia Demo Robot layer palletising gripper — UHT cartons
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-020

TA-26-020

Complete On track

Robot layer palletising gripper — UHT cartons · Fonterra Australia · Robot layer palletising

Value
$128,000
budget cost $93k
Cost to date
$58,565
$16k parts · $42k labour
Forecast margin
27.5%
$35,196
Claimed
100%
$128,000 of $128,000
FAT
22 Jul
signed off
Parts short
0
BOM covered
Bill of materials
12 lines · $16,495 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
AM8053-1J20 Beckhoff AM8053 servo motor, 4.0 Nm
Drives & controls · 0 ea free
2 2 — — $2,240.00 $4,480
AX5203-0000 Beckhoff AX5203 2-ch servo drive
Drives & controls · 0 ea free
1 1 — — $2,960.00 $2,960
E4-1-12-15-0 igus E4.1 energy chain, per metre
Drives & controls · 18 m free
3 3 — — $64.00 $192
SHCS-M10-30 Socket head cap screw M10 × 30, 12.9 (box 50)
Fasteners · 15 box free
2 2 — — $38.00 $76
DSBC-50-200-PPVA Festo DSBC standard cylinder Ø50 × 200
Pneumatics · 10 ea free
4 4 — — $268.00 $1,072
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
14 14 — — $21.00 $294
AL6061-PL20 Aluminium plate 6061-T6, 20 mm, 2400 × 1200
Raw material · 4 sheet free
1 1 — — $1,260.00 $1,260
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
6 6 — — $58.00 $348
WTB4-3P2161 SICK WTB4 photoelectric sensor
Sensors & safety · 22 ea free
4 4 — — $142.00 $568
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
1 1 — — $1,380.00 $1,380
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
1 1 — — $145.00 $145
TRK-RLR-CF12 Carbon fibre roller — 1200 mm (layer gripper)
Trak products · 0 ea free
12 12 — — $310.00 $3,720
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 04 May 2026 19 May 2026 12 Daniel Pham
Procurement Procurement 14 May 2026 27 May 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 22 May 2026 02 Jun 2026 8 Ben Nguyen
Assembly Gripper assembly bench 06 Jul 2026 21 Jul 2026 12 Tom Kowalski
Controls Controls & robot programming 13 Jul 2026 22 Jul 2026 8 Luke Brennan
FAT FAT cell 22 Jul 2026 23 Jul 2026 2 Matt O'Connor
Commissioning Site crew 12 Aug 2026 14 Aug 2026 3 Steve Hargreaves
Time booked
479.0 h · $42,070 at cost rates
Josh Mitchell83.0 h · $8,300
Daniel Pham73.5 h · $6,983
Tom Kowalski59.0 h · $4,248
Priya Raman59.0 h · $5,310
Ryan Walsh53.0 h · $3,816
Luke Brennan51.0 h · $5,355
Ben Nguyen41.0 h · $3,034
Steve Hargreaves33.0 h · $2,904
Matt O'Connor26.5 h · $2,120
DateWhoTaskHoursCost
05 Aug 2026Steve HargreavesSite commissioning 1.5$132
04 Aug 2026Luke BrennanSite commissioning 8.0$840
03 Aug 2026Luke BrennanSite commissioning 4.0$420
31 Jul 2026Luke BrennanSite commissioning 4.0$420
30 Jul 2026Steve HargreavesSite commissioning 7.5$660
29 Jul 2026Steve HargreavesSite commissioning 4.0$352
28 Jul 2026Luke BrennanSite commissioning 8.0$840
27 Jul 2026Steve HargreavesSite commissioning 4.0$352
24 Jul 2026Steve HargreavesSite commissioning 8.0$704
23 Jul 2026Steve HargreavesSite commissioning 4.0$352
22 Jul 2026Steve HargreavesSite commissioning 4.0$352
21 Jul 2026Luke BrennanSite commissioning 4.0$420
07 Jul 2026Tom KowalskiMechanical assembly 3.5$252
06 Jul 2026Tom KowalskiMechanical assembly 8.0$576
03 Jul 2026Ryan WalshMechanical assembly 6.0$432
02 Jul 2026Ryan WalshMechanical assembly 7.5$540
01 Jul 2026Tom KowalskiMechanical assembly 7.5$540
30 Jun 2026Ryan WalshMechanical assembly 4.0$288
29 Jun 2026Matt O'ConnorFAT 3.0$240
29 Jun 2026Ryan WalshMechanical assembly 6.0$432
26 Jun 2026Matt O'ConnorFAT 7.5$600
26 Jun 2026Josh MitchellPLC & robot programming 0.5$50
26 Jun 2026Ryan WalshMechanical assembly 4.0$288
25 Jun 2026Matt O'ConnorFAT 8.0$640
25 Jun 2026Josh MitchellPLC & robot programming 7.5$750
25 Jun 2026Ryan WalshMechanical assembly 6.0$432
24 Jun 2026Matt O'ConnorFAT 8.0$640
24 Jun 2026Luke BrennanPLC & robot programming 7.5$788
24 Jun 2026Ryan WalshMechanical assembly 6.0$432
23 Jun 2026Luke BrennanFAT 4.0$420
23 Jun 2026Josh MitchellPLC & robot programming 4.0$400
23 Jun 2026Tom KowalskiMechanical assembly 6.0$432
22 Jun 2026Josh MitchellPLC & robot programming 8.0$800
22 Jun 2026Tom KowalskiMechanical assembly 8.0$576
19 Jun 2026Josh MitchellPLC & robot programming 7.5$750
19 Jun 2026Tom KowalskiMechanical assembly 6.0$432
18 Jun 2026Josh MitchellPLC & robot programming 7.5$750
18 Jun 2026Tom KowalskiMechanical assembly 6.0$432
17 Jun 2026Josh MitchellPLC & robot programming 7.5$750
17 Jun 2026Tom KowalskiMechanical assembly 8.0$576
16 Jun 2026Josh MitchellPLC & robot programming 7.5$750
16 Jun 2026Ryan WalshMechanical assembly 6.0$432
15 Jun 2026Luke BrennanPLC & robot programming 6.0$630
15 Jun 2026Tom KowalskiMechanical assembly 6.0$432
12 Jun 2026Josh MitchellPLC & robot programming 8.0$800
12 Jun 2026Ryan WalshMechanical assembly 7.5$540
09 Jun 2026Ben NguyenMachining & fit-up 3.0$222
08 Jun 2026Ben NguyenMachining & fit-up 4.0$296
05 Jun 2026Ben NguyenMachining & fit-up 6.0$444
04 Jun 2026Ben NguyenMachining & fit-up 8.0$592
03 Jun 2026Ben NguyenMachining & fit-up 4.0$296
02 Jun 2026Ben NguyenMachining & fit-up 4.0$296
01 Jun 2026Ben NguyenMachining & fit-up 4.0$296
29 May 2026Ben NguyenMachining & fit-up 8.0$592
29 May 2026Daniel PhamMechanical design 5.0$475
28 May 2026Daniel PhamMechanical design 8.0$760
27 May 2026Daniel PhamMechanical design 6.0$570
26 May 2026Priya RamanMechanical design 8.0$720
25 May 2026Daniel PhamMechanical design 7.5$713
22 May 2026Daniel PhamMechanical design 6.0$570
Project
Customer
Fonterra Australia
Tim O'Brien · Engineering Lead
Site
Fonterra Australia — Stanhope
Robot
Motoman PL190 (existing)
PM
Sebastian
Quote
Q-26-0047
Customer PO
FON-PO-4582073
Key dates
Start
04 May 2026
FAT
22 Jul 2026
Ship
29 Jul 2026
Commissioning
12 Aug 2026
Completed
12 Aug 2026
Money
Value
$128,000
Budget cost
$92,804
Parts committed
$16,495
Parts issued
$16,495
Labour to date
$42,070
Forecast cost
$92,804
Forecast margin
$35,196 · 27.5%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0047 won — project TA-26-020 opened.
29 Apr, 10:39am · Craig Kirkpatrick