TA-26-035 · Snackbrands Australia Demo Side clamp servo palletising gripper — shelf-ready cartons
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-035

TA-26-035

FAT On track

Side clamp servo palletising gripper — shelf-ready cartons · Snackbrands Australia · Side clamp servo palletising

Value
$92,000
budget cost $65k
Cost to date
$31,160
$10k parts · $21k labour
Forecast margin
29.5%
$27,118
Claimed
30%
$27,600 of $92,000
FAT
8 Oct
in 2 days
Parts short
0
BOM covered
Bill of materials
13 lines · $9,992 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
AM8042-1F20 Beckhoff AM8042 servo motor, 1.4 Nm
Drives & controls · 1 ea free
1 1 — — $1,380.00 $1,380
M12-5P-5M M12 5-pin cable, 5 m, PUR
Electrical · 72 ea free
6 6 — — $24.00 $144
SHCS-M8-25 Socket head cap screw M8 × 25, 12.9 (box 100)
Fasteners · 18 box free
1 1 — — $34.00 $34
ADN-32-40-A-P-A Festo ADN compact cylinder Ø32 × 40
Pneumatics · 22 ea free
2 2 — — $118.00 $236
VTUG-10-8M Festo VTUG valve terminal, 8 stations, IO-Link
Pneumatics · 5 ea free
1 1 — — $1,290.00 $1,290
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
6 6 — — $21.00 $126
AL6061-PL10 Aluminium plate 6061-T6, 10 mm, 2400 × 1200
Raw material · 7 sheet free
1 1 — — $640.00 $640
CF-PLATE-6 Carbon fibre plate 6 mm, 1000 × 600
Raw material · 3 sheet free
1 1 — — $545.00 $545
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
4 4 — — $58.00 $232
TRK-CSS-M Compliance shock sensor — medium (≤150 kg tooling)
Trak products · 10 ea free
1 1 — — $1,020.00 $1,020
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
1 1 — — $145.00 $145
TRK-SP-SCS Side clamp plate — carbon fibre, 1250 mm
Trak products · 2 ea free
2 2 — — $680.00 $1,360
GEP2016IL-00-B Zimmer GEP2016IL electric parallel gripper, IO-Link
Zimmer components · 7 ea free
2 2 — — $1,420.00 $2,840
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $27,60030% of $92,000
Deposit 30%
INV-10458
$27,600 ex GST · $30,360 inc
PaidXero synced
FAT 40%
$36,800
not raised
Commissioning 30%
$27,600
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 13 Jul 2026 28 Jul 2026 12 Daniel Pham
Procurement Procurement 23 Jul 2026 05 Aug 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 31 Jul 2026 11 Aug 2026 8 Ben Nguyen
Assembly Gripper assembly bench 22 Sep 2026 07 Oct 2026 12 Tom Kowalski
Controls Controls & robot programming 29 Sep 2026 08 Oct 2026 8 Josh Mitchell
FAT FAT cell 08 Oct 2026 09 Oct 2026 2 Matt O'Connor
Commissioning Site crew 21 Oct 2026 23 Oct 2026 3 Steve Hargreaves
Time booked
243.5 h · $21,168 at cost rates
Priya Raman44.5 h · $4,005
Ryan Walsh36.5 h · $2,628
Daniel Pham35.5 h · $3,373
Luke Brennan33.5 h · $3,518
Tom Kowalski31.0 h · $2,232
Josh Mitchell28.0 h · $2,800
Ben Nguyen24.5 h · $1,813
Matt O'Connor10.0 h · $800
DateWhoTaskHoursCost
09 Sep 2026Ryan WalshMechanical assembly 1.5$108
08 Sep 2026Tom KowalskiMechanical assembly 4.0$288
07 Sep 2026Ryan WalshMechanical assembly 7.5$540
04 Sep 2026Matt O'ConnorFAT 2.0$160
04 Sep 2026Ryan WalshMechanical assembly 7.5$540
03 Sep 2026Matt O'ConnorFAT 8.0$640
03 Sep 2026Tom KowalskiMechanical assembly 7.5$540
02 Sep 2026Tom KowalskiMechanical assembly 4.0$288
01 Sep 2026Tom KowalskiMechanical assembly 4.0$288
31 Aug 2026Ryan WalshMechanical assembly 4.0$288
28 Aug 2026Ryan WalshMechanical assembly 4.0$288
27 Aug 2026Tom KowalskiMechanical assembly 7.5$540
26 Aug 2026Luke BrennanPLC & robot programming 7.5$788
26 Aug 2026Ryan WalshMechanical assembly 4.0$288
25 Aug 2026Josh MitchellPLC & robot programming 7.5$750
25 Aug 2026Ryan WalshMechanical assembly 8.0$576
24 Aug 2026Josh MitchellPLC & robot programming 8.0$800
24 Aug 2026Tom KowalskiMechanical assembly 4.0$288
21 Aug 2026Luke BrennanPLC & robot programming 8.0$840
20 Aug 2026Josh MitchellPLC & robot programming 6.0$600
19 Aug 2026Luke BrennanPLC & robot programming 6.0$630
12 Aug 2026Ben NguyenMachining & fit-up 2.5$185
11 Aug 2026Ben NguyenMachining & fit-up 6.0$444
10 Aug 2026Ben NguyenMachining & fit-up 8.0$592
07 Aug 2026Ben NguyenMachining & fit-up 8.0$592
31 Jul 2026Priya RamanMechanical design 4.0$360
30 Jul 2026Daniel PhamMechanical design 4.0$380
29 Jul 2026Priya RamanMechanical design 7.5$675
28 Jul 2026Priya RamanMechanical design 7.5$675
27 Jul 2026Daniel PhamMechanical design 6.0$570
24 Jul 2026Daniel PhamMechanical design 7.5$713
23 Jul 2026Daniel PhamMechanical design 4.0$380
22 Jul 2026Priya RamanMechanical design 4.0$360
21 Jul 2026Josh MitchellControls design 0.5$50
21 Jul 2026Daniel PhamMechanical design 6.0$570
20 Jul 2026Luke BrennanControls design 8.0$840
20 Jul 2026Daniel PhamMechanical design 8.0$760
17 Jul 2026Luke BrennanControls design 4.0$420
17 Jul 2026Priya RamanMechanical design 6.0$540
16 Jul 2026Josh MitchellControls design 6.0$600
16 Jul 2026Priya RamanMechanical design 7.5$675
15 Jul 2026Priya RamanMechanical design 8.0$720
Project
Customer
Snackbrands Australia
Nathan Kerr · Operations Engineering Manager
Site
Snackbrands Australia — Smithfield
Robot
ABB IRB 460 (existing)
PM
Sebastian
Quote
Q-26-0053
Customer PO
SNA-PO-4574347
Key dates
Start
13 Jul 2026
FAT
08 Oct 2026
Ship
14 Oct 2026
Commissioning
21 Oct 2026
Money
Value
$92,000
Budget cost
$64,882
Parts committed
$9,992
Parts issued
$9,992
Labour to date
$21,168
Forecast cost
$64,882
Forecast margin
$27,118 · 29.5%
Notes

FAT Thursday 8 Oct with Nathan and Melissa from Snackbrands on site at Ferntree Gully.

Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Activity
Confirmed FAT 8 Oct with Nathan.
1 Oct, 8:28am · Craig Kirkpatrick
Quote Q-26-0053 won — project TA-26-035 opened.
9 Jul, 10:30am · Craig Kirkpatrick