Trak
Trak
TA-26-036 · Fibre King Demo Robot roller layer palletising grippers ×2
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-036

TA-26-036

Procurement On track

Robot roller layer palletising grippers ×2 · Fibre King · Robot layer palletising

Value
$146,000
budget cost $101k
Cost to date
$13,408
$0 parts · $13k labour
Forecast margin
30.3%
$44,300
Claimed
30%
$43,800 of $146,000
FAT
18 Nov
in 43 days
Parts short
1
all on order
Bill of materials
12 lines · $32,990 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
AM8053-1J20 Beckhoff AM8053 servo motor, 4.0 Nm
Drives & controls · 0 ea free
4 — 2 2
4 on order
$2,240.00 $8,960
AX5203-0000 Beckhoff AX5203 2-ch servo drive
Drives & controls · 0 ea free
2 — 2 — $2,960.00 $5,920
E4-1-12-15-0 igus E4.1 energy chain, per metre
Drives & controls · 18 m free
6 — 6 — $64.00 $384
SHCS-M10-30 Socket head cap screw M10 × 30, 12.9 (box 50)
Fasteners · 15 box free
4 — 4 — $38.00 $152
DSBC-50-200-PPVA Festo DSBC standard cylinder Ø50 × 200
Pneumatics · 10 ea free
8 — 8 — $268.00 $2,144
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
28 — 28 — $21.00 $588
AL6061-PL20 Aluminium plate 6061-T6, 20 mm, 2400 × 1200
Raw material · 4 sheet free
2 — 2 — $1,260.00 $2,520
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
12 — 12 — $58.00 $696
WTB4-3P2161 SICK WTB4 photoelectric sensor
Sensors & safety · 22 ea free
8 — 8 — $142.00 $1,136
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
2 — 2 — $1,380.00 $2,760
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
2 — 2 — $145.00 $290
TRK-RLR-CF12 Carbon fibre roller — 1200 mm (layer gripper)
Trak products · 0 ea free
24 — 24 — $310.00 $7,440
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $43,80030% of $146,000
Deposit 30%
INV-10459
$43,800 ex GST · $48,180 inc
PaidXero synced
FAT 40%
$58,400
not raised
Commissioning 30%
$43,800
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 31 Aug 2026 15 Sep 2026 12 Priya Raman
Procurement Procurement 10 Sep 2026 23 Sep 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 18 Sep 2026 29 Sep 2026 8 Ben Nguyen
Assembly Gripper assembly bench 02 Nov 2026 17 Nov 2026 12 Tom Kowalski
Controls Controls & robot programming 09 Nov 2026 18 Nov 2026 8 Luke Brennan
FAT FAT cell 18 Nov 2026 19 Nov 2026 2 Matt O'Connor
Commissioning Site crew 02 Dec 2026 04 Dec 2026 3 Steve Hargreaves
Time booked
142.0 h · $13,408 at cost rates
Daniel Pham59.0 h · $5,605
Priya Raman56.5 h · $5,085
Luke Brennan13.5 h · $1,418
Josh Mitchell13.0 h · $1,300
DateWhoTaskHoursCost
24 Sep 2026Priya RamanMechanical design 6.5$585
23 Sep 2026Daniel PhamMechanical design 6.0$570
22 Sep 2026Priya RamanMechanical design 7.5$675
21 Sep 2026Daniel PhamMechanical design 8.0$760
18 Sep 2026Priya RamanMechanical design 6.0$540
17 Sep 2026Daniel PhamMechanical design 8.0$760
16 Sep 2026Daniel PhamMechanical design 6.0$570
15 Sep 2026Priya RamanMechanical design 7.5$675
14 Sep 2026Priya RamanMechanical design 4.0$360
11 Sep 2026Daniel PhamMechanical design 8.0$760
10 Sep 2026Daniel PhamMechanical design 8.0$760
09 Sep 2026Daniel PhamMechanical design 7.5$713
08 Sep 2026Priya RamanMechanical design 6.0$540
07 Sep 2026Josh MitchellControls design 1.0$100
07 Sep 2026Priya RamanMechanical design 4.0$360
04 Sep 2026Josh MitchellControls design 4.0$400
04 Sep 2026Priya RamanMechanical design 7.5$675
03 Sep 2026Luke BrennanControls design 7.5$788
03 Sep 2026Daniel PhamMechanical design 7.5$713
02 Sep 2026Luke BrennanControls design 6.0$630
02 Sep 2026Priya RamanMechanical design 7.5$675
01 Sep 2026Josh MitchellControls design 8.0$800
Project
Customer
Fibre King
Greg Hollis · Engineering Manager
Site
Fibre King — Dandenong South
Robot
FANUC M-410iC (existing)
PM
Sebastian
Quote
Q-26-0054
Customer PO
FIB-PO-4509070
Key dates
Start
31 Aug 2026
FAT
18 Nov 2026
Ship
25 Nov 2026
Commissioning
02 Dec 2026
Money
Value
$146,000
Budget cost
$100,658
Parts committed
$32,990
Parts issued
$0
Labour to date
$13,408
Forecast cost
$101,700
Forecast margin
$44,300 · 30.3%
Purchase orders
All POs
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0054 won — project TA-26-036 opened.
27 Aug, 10:04am · Craig Kirkpatrick