Projects / TA-26-047
TA-26-047
Design On trackRobot roller layer palletising gripper · Bega Cheese · Robot layer palletising
Value
$134,000
budget cost $99k
Cost to date
$9,048
$0 parts · $9k labour
Forecast margin
24.9%
$33,375
Claimed
30%
$40,200 of $134,000
FAT
16 Dec
in 71 days
Parts short
3
3 not on order
Bill of materials
12 lines · $16,495 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| AM8053-1J20 | Beckhoff AM8053 servo motor, 4.0 Nm Drives & controls · 0 ea free | 2 | — | — | 2 | $2,240.00 | $4,480 | |
| AX5203-0000 | Beckhoff AX5203 2-ch servo drive Drives & controls · 0 ea free | 1 | — | 1 | — | $2,960.00 | $2,960 | |
| E4-1-12-15-0 | igus E4.1 energy chain, per metre Drives & controls · 18 m free | 3 | — | 3 | — | $64.00 | $192 | |
| SHCS-M10-30 | Socket head cap screw M10 × 30, 12.9 (box 50) Fasteners · 15 box free | 2 | — | 2 | — | $38.00 | $76 | |
| DSBC-50-200-PPVA | Festo DSBC standard cylinder Ø50 × 200 Pneumatics · 10 ea free | 4 | — | 4 | — | $268.00 | $1,072 | |
| AL-PROF-4545 | Aluminium profile 45 × 45, per metre Raw material · 108 m free | 14 | — | 14 | — | $21.00 | $294 | |
| AL6061-PL20 | Aluminium plate 6061-T6, 20 mm, 2400 × 1200 Raw material · 4 sheet free | 1 | — | 1 | — | $1,260.00 | $1,260 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 6 | — | 6 | — | $58.00 | $348 | |
| WTB4-3P2161 | SICK WTB4 photoelectric sensor Sensors & safety · 22 ea free | 4 | — | 4 | — | $142.00 | $568 | |
| TRK-CSS-L | Compliance shock sensor — large (≤300 kg tooling) Trak products · 0 ea free | 1 | — | — | 1 | $1,380.00 | $1,380 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 1 | — | 1 | — | $145.00 | $145 | |
| TRK-RLR-CF12 | Carbon fibre roller — 1200 mm (layer gripper) Trak products · 0 ea free | 12 | — | 8 | 4 | $310.00 | $3,720 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $40,20030% of $134,000
Deposit 30%
INV-10472
$40,200 ex GST · $44,220 inc
Awaiting paymentXero synced
FAT 40%
$53,600
not raised
Commissioning 30%
$40,200
not raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 28 Sep 2026 | 13 Oct 2026 | 12 | Daniel Pham | |
| Procurement | Procurement | 08 Oct 2026 | 21 Oct 2026 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 16 Oct 2026 | 27 Oct 2026 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 30 Nov 2026 | 15 Dec 2026 | 12 | Tom Kowalski | |
| Controls | Controls & robot programming | 07 Dec 2026 | 16 Dec 2026 | 8 | Josh Mitchell | |
| FAT | FAT cell | 16 Dec 2026 | 17 Dec 2026 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 27 Jan 2027 | 29 Jan 2027 | 3 | Steve Hargreaves |
Time booked
96.0 h · $9,048 at cost rates
Priya Raman50.5 h · $4,545
Daniel Pham27.5 h · $2,613
Luke Brennan18.0 h · $1,890
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 06 Oct 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 06 Oct 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 06 Oct 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 06 Oct 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 06 Oct 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 06 Oct 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 06 Oct 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 05 Oct 2026 | Luke Brennan | Controls design | 4.0 | $420 | |
| 05 Oct 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 02 Oct 2026 | Luke Brennan | Controls design | 8.0 | $840 | |
| 02 Oct 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 01 Oct 2026 | Luke Brennan | Controls design | 6.0 | $630 | |
| 01 Oct 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 30 Sep 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 29 Sep 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 28 Sep 2026 | Daniel Pham | Mechanical design | 4.0 | $380 |
Project
- Customer
- Bega CheeseRoss Henderson · Site Engineering Manager
- Site
- Bega Cheese — Bega
- Robot
- ABB IRB 660 (existing)
- PM
- Sebastian
- Quote
- Q-26-0065
- Customer PO
- BEG-PO-4561553
Key dates
- Start
- 28 Sep 2026
- FAT
- 16 Dec 2026
- Ship
- 21 Dec 2026
- Commissioning
- 27 Jan 2027
Money
- Value
- $134,000
- Budget cost
- $99,325
- Parts committed
- $16,495
- Parts issued
- $0
- Labour to date
- $9,048
- Forecast cost
- $100,625
- Forecast margin
- $33,375 · 24.9%
Purchase orders
All POsNo purchase orders for this project.
Calendar
CalendarNothing in the calendar.
Activity
Quote Q-26-0065 won — project TA-26-047 opened.
23 Sep, 10:51am · Craig Kirkpatrick