Projects / TA-25-019
TA-25-019
Complete On trackVacuum palletising grippers ×2 — Line 4 PET · Coca-Cola Europacific Partners · Vacuum palletising
Value
$142,000
budget cost $107k
Cost to date
$62,325
$19k parts · $43k labour
Forecast margin
24.9%
$35,318
Claimed
100%
$142,000 of $142,000
FAT
20 Aug
signed off
Parts short
0
BOM covered
Bill of materials
13 lines · $19,374 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| SHCS-M8-25 | Socket head cap screw M8 × 25, 12.9 (box 100) Fasteners · 18 box free | 2 | 2 | — | — | $34.00 | $68 | |
| KQ2H08-02AS | SMC push-in fitting 8 mm (bag 10) Pneumatics · 27 bag free | 4 | 4 | — | — | $21.00 | $84 | |
| VTUG-10-8M | Festo VTUG valve terminal, 8 stations, IO-Link Pneumatics · 5 ea free | 2 | 2 | — | — | $1,290.00 | $2,580 | |
| ZH13DS-06-06-08 | SMC ZH vacuum ejector, Ø1.3 nozzle Pneumatics · 18 ea free | 12 | 12 | — | — | $96.00 | $1,152 | |
| AL-PROF-4545 | Aluminium profile 45 × 45, per metre Raw material · 108 m free | 16 | 16 | — | — | $21.00 | $336 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 4 | 4 | — | — | $58.00 | $232 | |
| WTB4-3P2161 | SICK WTB4 photoelectric sensor Sensors & safety · 22 ea free | 4 | 4 | — | — | $142.00 | $568 | |
| TRK-CSS-M | Compliance shock sensor — medium (≤150 kg tooling) Trak products · 10 ea free | 2 | 2 | — | — | $1,020.00 | $2,040 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 2 | 2 | — | — | $145.00 | $290 | |
| TRK-SLR-01 | Vacuum slip ring — robot axis 6 Trak products · 4 ea free | 2 | 2 | — | — | $1,240.00 | $2,480 | |
| TRK-VFRM-AN | Vacuum gripper frame — anodised aluminium (machined) Trak products · 1 ea free | 2 | 2 | — | — | $2,400.00 | $4,800 | |
| PIAB-B75-2 | Piab B75-2 bellows suction cup, NBR Vacuum · 87 ea free | 48 | 48 | — | — | $38.00 | $1,824 | |
| PICOMPACT-23 | Piab piCOMPACT23 vacuum pump, energy saving Vacuum · 0 ea free | 2 | 2 | — | — | $1,460.00 | $2,920 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 16 Jun 2025 | 01 Jul 2025 | 12 | Daniel Pham | |
| Procurement | Procurement | 26 Jun 2025 | 09 Jul 2025 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 04 Jul 2025 | 15 Jul 2025 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 04 Aug 2025 | 19 Aug 2025 | 12 | Tom Kowalski | |
| Controls | Controls & robot programming | 11 Aug 2025 | 20 Aug 2025 | 8 | Luke Brennan | |
| FAT | FAT cell | 20 Aug 2025 | 21 Aug 2025 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 08 Sep 2025 | 10 Sep 2025 | 3 | Steve Hargreaves |
Time booked
483.0 h · $42,951 at cost rates
Luke Brennan107.5 h · $11,288
Daniel Pham84.5 h · $8,028
Tom Kowalski57.5 h · $4,140
Ryan Walsh55.5 h · $3,996
Priya Raman49.0 h · $4,410
Ben Nguyen41.0 h · $3,034
Josh Mitchell39.0 h · $3,900
Steve Hargreaves29.5 h · $2,596
Matt O'Connor19.5 h · $1,560
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 17 Sep 2025 | Luke Brennan | Site commissioning | 4.5 | $473 | |
| 16 Sep 2025 | Steve Hargreaves | Site commissioning | 7.5 | $660 | |
| 15 Sep 2025 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 12 Sep 2025 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 11 Sep 2025 | Luke Brennan | Site commissioning | 8.0 | $840 | |
| 10 Sep 2025 | Luke Brennan | Site commissioning | 7.5 | $788 | |
| 09 Sep 2025 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 08 Sep 2025 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 05 Sep 2025 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 04 Sep 2025 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 03 Sep 2025 | Steve Hargreaves | Site commissioning | 4.0 | $352 | |
| 02 Sep 2025 | Steve Hargreaves | Site commissioning | 6.0 | $528 | |
| 20 Aug 2025 | Tom Kowalski | Mechanical assembly | 4.5 | $324 | |
| 19 Aug 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 18 Aug 2025 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 15 Aug 2025 | Ryan Walsh | Mechanical assembly | 8.0 | $576 | |
| 14 Aug 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 13 Aug 2025 | Matt O'Connor | FAT | 5.5 | $440 | |
| 13 Aug 2025 | Ryan Walsh | Mechanical assembly | 8.0 | $576 | |
| 12 Aug 2025 | Luke Brennan | FAT | 7.5 | $788 | |
| 12 Aug 2025 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 11 Aug 2025 | Matt O'Connor | FAT | 8.0 | $640 | |
| 11 Aug 2025 | Ryan Walsh | Mechanical assembly | 7.5 | $540 | |
| 08 Aug 2025 | Matt O'Connor | FAT | 6.0 | $480 | |
| 08 Aug 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 07 Aug 2025 | Luke Brennan | FAT | 4.0 | $420 | |
| 07 Aug 2025 | Tom Kowalski | Mechanical assembly | 8.0 | $576 | |
| 06 Aug 2025 | Josh Mitchell | PLC & robot programming | 4.0 | $400 | |
| 06 Aug 2025 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 05 Aug 2025 | Luke Brennan | PLC & robot programming | 8.0 | $840 | |
| 05 Aug 2025 | Ryan Walsh | Mechanical assembly | 8.0 | $576 | |
| 04 Aug 2025 | Josh Mitchell | PLC & robot programming | 6.0 | $600 | |
| 04 Aug 2025 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 01 Aug 2025 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 01 Aug 2025 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 31 Jul 2025 | Luke Brennan | PLC & robot programming | 6.0 | $630 | |
| 31 Jul 2025 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 30 Jul 2025 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 30 Jul 2025 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 29 Jul 2025 | Josh Mitchell | PLC & robot programming | 6.0 | $600 | |
| 29 Jul 2025 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 28 Jul 2025 | Josh Mitchell | PLC & robot programming | 6.0 | $600 | |
| 28 Jul 2025 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 25 Jul 2025 | Luke Brennan | PLC & robot programming | 6.0 | $630 | |
| 24 Jul 2025 | Josh Mitchell | PLC & robot programming | 7.5 | $750 | |
| 23 Jul 2025 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 21 Jul 2025 | Ben Nguyen | Machining & fit-up | 2.0 | $148 | |
| 18 Jul 2025 | Ben Nguyen | Machining & fit-up | 7.5 | $555 | |
| 17 Jul 2025 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 16 Jul 2025 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 16 Jul 2025 | Daniel Pham | Mechanical design | 0.5 | $48 | |
| 15 Jul 2025 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 15 Jul 2025 | Daniel Pham | Mechanical design | 6.0 | $570 | |
| 14 Jul 2025 | Ben Nguyen | Machining & fit-up | 7.5 | $555 | |
| 14 Jul 2025 | Daniel Pham | Mechanical design | 6.0 | $570 | |
| 11 Jul 2025 | Ben Nguyen | Machining & fit-up | 8.0 | $592 | |
| 11 Jul 2025 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 10 Jul 2025 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 09 Jul 2025 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 08 Jul 2025 | Daniel Pham | Mechanical design | 8.0 | $760 |
Project
- Customer
- Coca-Cola Europacific PartnersAndrew Fitzgerald · Engineering Manager — Moorebank
- Site
- Coca-Cola Europacific Partners — Moorebank
- Robot
- FANUC M-410iC (existing)
- PM
- Sebastian
- Quote
- Q-25-0060
- Customer PO
- CCE-PO-4512871
Key dates
- Start
- 16 Jun 2025
- FAT
- 20 Aug 2025
- Ship
- 27 Aug 2025
- Commissioning
- 08 Sep 2025
- Completed
- 08 Sep 2025
Money
- Value
- $142,000
- Budget cost
- $106,682
- Parts committed
- $19,374
- Parts issued
- $19,374
- Labour to date
- $42,951
- Forecast cost
- $106,682
- Forecast margin
- $35,318 · 24.9%
Purchase orders
All POsNo purchase orders for this project.
Calendar
CalendarNothing in the calendar.
Activity
Quote Q-25-0060 won — project TA-25-019 opened.
12 Jun, 10:56am · Craig Kirkpatrick