Projects / TA-26-008
TA-26-008
Complete On trackVacuum palletising gripper with slip sheet attachment · Sanitarium Health Food Company · Vacuum palletising
Value
$88,400
budget cost $58k
Cost to date
$32,486
$10k parts · $23k labour
Forecast margin
34.6%
$30,548
Claimed
100%
$88,400 of $88,400
FAT
8 Apr
signed off
Parts short
0
BOM covered
Bill of materials
13 lines · $9,687 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| SHCS-M8-25 | Socket head cap screw M8 × 25, 12.9 (box 100) Fasteners · 18 box free | 1 | 1 | — | — | $34.00 | $34 | |
| KQ2H08-02AS | SMC push-in fitting 8 mm (bag 10) Pneumatics · 27 bag free | 2 | 2 | — | — | $21.00 | $42 | |
| VTUG-10-8M | Festo VTUG valve terminal, 8 stations, IO-Link Pneumatics · 5 ea free | 1 | 1 | — | — | $1,290.00 | $1,290 | |
| ZH13DS-06-06-08 | SMC ZH vacuum ejector, Ø1.3 nozzle Pneumatics · 18 ea free | 6 | 6 | — | — | $96.00 | $576 | |
| AL-PROF-4545 | Aluminium profile 45 × 45, per metre Raw material · 108 m free | 8 | 8 | — | — | $21.00 | $168 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 2 | 2 | — | — | $58.00 | $116 | |
| WTB4-3P2161 | SICK WTB4 photoelectric sensor Sensors & safety · 22 ea free | 2 | 2 | — | — | $142.00 | $284 | |
| TRK-CSS-M | Compliance shock sensor — medium (≤150 kg tooling) Trak products · 10 ea free | 1 | 1 | — | — | $1,020.00 | $1,020 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 1 | 1 | — | — | $145.00 | $145 | |
| TRK-SLR-01 | Vacuum slip ring — robot axis 6 Trak products · 4 ea free | 1 | 1 | — | — | $1,240.00 | $1,240 | |
| TRK-VFRM-AN | Vacuum gripper frame — anodised aluminium (machined) Trak products · 1 ea free | 1 | 1 | — | — | $2,400.00 | $2,400 | |
| PIAB-B75-2 | Piab B75-2 bellows suction cup, NBR Vacuum · 87 ea free | 24 | 24 | — | — | $38.00 | $912 | |
| PICOMPACT-23 | Piab piCOMPACT23 vacuum pump, energy saving Vacuum · 0 ea free | 1 | 1 | — | — | $1,460.00 | $1,460 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 02 Feb 2026 | 17 Feb 2026 | 12 | Daniel Pham | |
| Procurement | Procurement | 12 Feb 2026 | 25 Feb 2026 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 20 Feb 2026 | 03 Mar 2026 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 23 Mar 2026 | 07 Apr 2026 | 12 | Tom Kowalski | |
| Controls | Controls & robot programming | 30 Mar 2026 | 08 Apr 2026 | 8 | Josh Mitchell | |
| FAT | FAT cell | 08 Apr 2026 | 09 Apr 2026 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 28 Apr 2026 | 30 Apr 2026 | 3 | Steve Hargreaves |
Time booked
253.5 h · $22,799 at cost rates
Luke Brennan69.0 h · $7,245
Daniel Pham47.0 h · $4,465
Ryan Walsh33.5 h · $2,412
Tom Kowalski26.0 h · $1,872
Priya Raman23.0 h · $2,070
Ben Nguyen21.5 h · $1,591
Josh Mitchell19.0 h · $1,900
Steve Hargreaves10.5 h · $924
Matt O'Connor4.0 h · $320
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 29 Apr 2026 | Steve Hargreaves | Site commissioning | 2.5 | $220 | |
| 28 Apr 2026 | Luke Brennan | Site commissioning | 6.0 | $630 | |
| 27 Apr 2026 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 24 Apr 2026 | Luke Brennan | Site commissioning | 4.0 | $420 | |
| 23 Apr 2026 | Luke Brennan | Site commissioning | 8.0 | $840 | |
| 22 Apr 2026 | Steve Hargreaves | Site commissioning | 8.0 | $704 | |
| 30 Mar 2026 | Luke Brennan | FAT | 2.0 | $210 | |
| 27 Mar 2026 | Matt O'Connor | FAT | 4.0 | $320 | |
| 26 Mar 2026 | Luke Brennan | FAT | 4.0 | $420 | |
| 26 Mar 2026 | Tom Kowalski | Mechanical assembly | 0.5 | $36 | |
| 25 Mar 2026 | Luke Brennan | FAT | 6.0 | $630 | |
| 25 Mar 2026 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 24 Mar 2026 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 23 Mar 2026 | Ryan Walsh | Mechanical assembly | 7.5 | $540 | |
| 20 Mar 2026 | Tom Kowalski | Mechanical assembly | 6.0 | $432 | |
| 19 Mar 2026 | Josh Mitchell | PLC & robot programming | 5.0 | $500 | |
| 19 Mar 2026 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 18 Mar 2026 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 18 Mar 2026 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 17 Mar 2026 | Josh Mitchell | PLC & robot programming | 6.0 | $600 | |
| 17 Mar 2026 | Ryan Walsh | Mechanical assembly | 6.0 | $432 | |
| 16 Mar 2026 | Luke Brennan | PLC & robot programming | 7.5 | $788 | |
| 16 Mar 2026 | Ryan Walsh | Mechanical assembly | 8.0 | $576 | |
| 13 Mar 2026 | Josh Mitchell | PLC & robot programming | 8.0 | $800 | |
| 13 Mar 2026 | Tom Kowalski | Mechanical assembly | 4.0 | $288 | |
| 12 Mar 2026 | Luke Brennan | PLC & robot programming | 4.0 | $420 | |
| 12 Mar 2026 | Tom Kowalski | Mechanical assembly | 7.5 | $540 | |
| 05 Mar 2026 | Ben Nguyen | Machining & fit-up | 3.5 | $259 | |
| 04 Mar 2026 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 03 Mar 2026 | Ben Nguyen | Machining & fit-up | 8.0 | $592 | |
| 02 Mar 2026 | Ben Nguyen | Machining & fit-up | 6.0 | $444 | |
| 24 Feb 2026 | Priya Raman | Mechanical design | 3.0 | $270 | |
| 23 Feb 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 20 Feb 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 19 Feb 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 18 Feb 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 17 Feb 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 16 Feb 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 13 Feb 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 12 Feb 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 11 Feb 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 10 Feb 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 09 Feb 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 06 Feb 2026 | Luke Brennan | Controls design | 6.0 | $630 | |
| 06 Feb 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 05 Feb 2026 | Luke Brennan | Controls design | 6.0 | $630 | |
| 05 Feb 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 04 Feb 2026 | Luke Brennan | Controls design | 4.0 | $420 |
Project
- Customer
- Sanitarium Health Food CompanyJonathan Reid · Engineering Manager
- Site
- Sanitarium Health Food Company — Berkeley Vale
- Robot
- FANUC M-410iC (existing)
- PM
- Sebastian
- Quote
- Q-26-0043
- Customer PO
- SAN-PO-4540284
Key dates
- Start
- 02 Feb 2026
- FAT
- 08 Apr 2026
- Ship
- 15 Apr 2026
- Commissioning
- 28 Apr 2026
- Completed
- 28 Apr 2026
Money
- Value
- $88,400
- Budget cost
- $57,852
- Parts committed
- $9,687
- Parts issued
- $9,687
- Labour to date
- $22,799
- Forecast cost
- $57,852
- Forecast margin
- $30,548 · 34.6%
Purchase orders
All POsNo purchase orders for this project.
Calendar
CalendarNothing in the calendar.
Activity
Quote Q-26-0043 won — project TA-26-008 opened.
25 Jan, 10:21am · Craig Kirkpatrick