TA-26-011 · Bundaberg Brewed Drinks Demo Pallet destrapping cell — glass bottle line
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-011

TA-26-011

Complete On track

Pallet destrapping cell — glass bottle line · Bundaberg Brewed Drinks · Pallet destrapping / debanding

Value
$421,000
budget cost $292k
Cost to date
$210,940
$122k parts · $89k labour
Forecast margin
30.6%
$128,637
Claimed
100%
$421,000 of $421,000
FAT
27 May
signed off
Parts short
0
BOM covered
Bill of materials
17 lines · $122,127 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CX5130-0125 Beckhoff CX5130 embedded PC (TwinCAT)
Drives & controls · 4 ea free
1 1 — — $2,480.00 $2,480
EK1100 Beckhoff EK1100 EtherCAT coupler
Drives & controls · 8 ea free
2 2 — — $215.00 $430
ENC-600-SS Control enclosure 600 × 600, stainless
Electrical · 2 ea free
1 1 — — $920.00 $920
VTUG-10-8M Festo VTUG valve terminal, 8 stations, IO-Link
Pneumatics · 5 ea free
1 1 — — $1,290.00 $1,290
SHS-50-3-8M Steel SHS 50 × 50 × 3, 8 m length
Raw material · 15 length free
4 4 — — $96.00 $384
IRB460-110 ABB IRB 460 palletising robot, 110 kg / 2.4 m
Robots · 0 ea free
1 1 — — $92,400.00 $92,400
C4P-SA15030A SICK deTec4 safety light curtain 1500 mm
Sensors & safety · 4 pair free
2 2 — — $2,140.00 $4,280
INSPECTORP621 SICK InspectorP621 vision sensor
Sensors & safety · 0 ea free
1 1 — — $3,890.00 $3,890
PNOZ-MB0 Pilz PNOZmulti 2 safety relay base unit
Sensors & safety · 4 ea free
1 1 — — $1,180.00 $1,180
WTB4-3P2161 SICK WTB4 photoelectric sensor
Sensors & safety · 22 ea free
4 4 — — $142.00 $568
XG-DOOR-SL Axelent sliding door kit with interlock
Sensors & safety · 2 ea free
1 1 — — $1,450.00 $1,450
XG-PANEL-2200 Axelent X-Guard mesh panel 2200 × 1500
Sensors & safety · 36 ea free
14 14 — — $168.00 $2,352
XG-POST-2200 Axelent X-Guard post 2200
Sensors & safety · 36 ea free
12 12 — — $64.00 $768
TRK-CHP-13 Strap chipper module — 13 mm cut
Trak products · 2 ea free
1 1 — — $6,850.00 $6,850
TRK-CSS-M Compliance shock sensor — medium (≤150 kg tooling)
Trak products · 10 ea free
1 1 — — $1,020.00 $1,020
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
1 1 — — $145.00 $145
GPP5013N-00-A Zimmer GPP5013N pneumatic parallel gripper
Zimmer components · 10 ea free
2 2 — — $860.00 $1,720
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 16 Feb 2026 13 Mar 2026 20 Daniel Pham
Procurement Procurement 06 Mar 2026 26 Mar 2026 15 Jess Taylor
Fabrication Excelfab — laser, fold & weld 19 Mar 2026 03 Apr 2026 12 Ben Nguyen
Assembly Assembly bay 1 27 Apr 2026 26 May 2026 22 Tom Kowalski
Controls Controls & robot programming 08 May 2026 28 May 2026 15 Josh Mitchell
FAT FAT cell 27 May 2026 29 May 2026 3 Matt O'Connor
Commissioning Site crew 24 Jun 2026 03 Jul 2026 8 Steve Hargreaves
Time booked
997.5 h · $88,813 at cost rates
Luke Brennan219.5 h · $23,048
Daniel Pham139.5 h · $13,253
Priya Raman136.5 h · $12,285
Ryan Walsh127.0 h · $9,144
Tom Kowalski106.5 h · $7,668
Josh Mitchell102.5 h · $10,250
Ben Nguyen85.0 h · $6,290
Steve Hargreaves49.5 h · $4,356
Matt O'Connor31.5 h · $2,520
DateWhoTaskHoursCost
01 Jun 2026Steve HargreavesSite commissioning 0.5$44
29 May 2026Luke BrennanSite commissioning 6.0$630
28 May 2026Steve HargreavesSite commissioning 6.0$528
27 May 2026Steve HargreavesSite commissioning 4.0$352
26 May 2026Steve HargreavesSite commissioning 6.0$528
25 May 2026Luke BrennanSite commissioning 7.5$788
22 May 2026Luke BrennanSite commissioning 6.0$630
21 May 2026Luke BrennanSite commissioning 7.5$788
21 May 2026Ryan WalshMechanical assembly 4.5$324
20 May 2026Steve HargreavesSite commissioning 8.0$704
20 May 2026Ryan WalshMechanical assembly 4.0$288
19 May 2026Luke BrennanSite commissioning 6.0$630
19 May 2026Tom KowalskiMechanical assembly 6.0$432
18 May 2026Steve HargreavesSite commissioning 4.0$352
18 May 2026Tom KowalskiMechanical assembly 4.0$288
15 May 2026Luke BrennanSite commissioning 4.0$420
15 May 2026Ryan WalshMechanical assembly 6.0$432
14 May 2026Luke BrennanSite commissioning 4.0$420
14 May 2026Ryan WalshMechanical assembly 8.0$576
13 May 2026Luke BrennanSite commissioning 7.5$788
13 May 2026Ryan WalshMechanical assembly 6.0$432
12 May 2026Steve HargreavesSite commissioning 7.5$660
12 May 2026Tom KowalskiMechanical assembly 7.5$540
11 May 2026Luke BrennanSite commissioning 7.5$788
11 May 2026Ryan WalshMechanical assembly 7.5$540
08 May 2026Steve HargreavesSite commissioning 7.5$660
08 May 2026Ryan WalshMechanical assembly 4.0$288
07 May 2026Luke BrennanSite commissioning 6.0$630
07 May 2026Ryan WalshMechanical assembly 8.0$576
06 May 2026Steve HargreavesSite commissioning 6.0$528
06 May 2026Ryan WalshMechanical assembly 4.0$288
05 May 2026Luke BrennanSite commissioning 8.0$840
05 May 2026Tom KowalskiMechanical assembly 4.0$288
04 May 2026Luke BrennanSite commissioning 8.0$840
04 May 2026Ryan WalshMechanical assembly 6.0$432
01 May 2026Tom KowalskiMechanical assembly 6.0$432
30 Apr 2026Tom KowalskiMechanical assembly 7.5$540
29 Apr 2026Tom KowalskiMechanical assembly 4.0$288
28 Apr 2026Josh MitchellPLC & robot programming 1.5$150
28 Apr 2026Ryan WalshMechanical assembly 6.0$432
27 Apr 2026Josh MitchellPLC & robot programming 6.0$600
27 Apr 2026Ryan WalshMechanical assembly 7.5$540
24 Apr 2026Luke BrennanPLC & robot programming 7.5$788
24 Apr 2026Ryan WalshMechanical assembly 6.0$432
23 Apr 2026Luke BrennanFAT 4.5$473
23 Apr 2026Josh MitchellPLC & robot programming 4.0$400
23 Apr 2026Tom KowalskiMechanical assembly 8.0$576
22 Apr 2026Luke BrennanFAT 7.5$788
22 Apr 2026Luke BrennanPLC & robot programming 6.0$630
22 Apr 2026Ryan WalshMechanical assembly 7.5$540
21 Apr 2026Matt O'ConnorFAT 4.0$320
21 Apr 2026Josh MitchellPLC & robot programming 4.0$400
21 Apr 2026Tom KowalskiMechanical assembly 4.0$288
21 Apr 2026Daniel PhamMechanical design 2.0$190
20 Apr 2026Matt O'ConnorFAT 8.0$640
20 Apr 2026Luke BrennanPLC & robot programming 4.0$420
20 Apr 2026Ryan WalshMechanical assembly 4.0$288
20 Apr 2026Priya RamanMechanical design 8.0$720
17 Apr 2026Luke BrennanFAT 8.0$840
17 Apr 2026Luke BrennanPLC & robot programming 4.0$420
Project
Customer
Bundaberg Brewed Drinks
Cameron Lee · Production Engineering Manager
Site
Bundaberg Brewed Drinks — Bundaberg
Robot
ABB IRB 460
PM
Sebastian
Quote
Q-26-0044
Customer PO
BUN-PO-4599658
Key dates
Start
16 Feb 2026
FAT
27 May 2026
Ship
03 Jun 2026
Commissioning
24 Jun 2026
Completed
24 Jun 2026
Money
Value
$421,000
Budget cost
$292,363
Parts committed
$122,127
Parts issued
$122,127
Labour to date
$88,813
Forecast cost
$292,363
Forecast margin
$128,637 · 30.6%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0044 won — project TA-26-011 opened.
7 Feb, 10:26am · Craig Kirkpatrick