TA-26-033

Fabrication On track

Vacuum palletising grippers ×3 — Lines 6–8 PET · Coca-Cola Europacific Partners · Vacuum palletising

Value
$168,000
budget cost $126k
Cost to date
$31,661
$10k parts · $22k labour
Forecast margin
25.0%
$42,061
Claimed
30%
$50,400 of $168,000
FAT
4 Nov
in 29 days
Parts short
1
all on order
Bill of materials
13 lines · $29,061 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
SHCS-M8-25 Socket head cap screw M8 × 25, 12.9 (box 100)
Fasteners · 18 box free
3 2 1 — $34.00 $102
KQ2H08-02AS SMC push-in fitting 8 mm (bag 10)
Pneumatics · 27 bag free
6 — 6 — $21.00 $126
VTUG-10-8M Festo VTUG valve terminal, 8 stations, IO-Link
Pneumatics · 5 ea free
3 — 3 — $1,290.00 $3,870
ZH13DS-06-06-08 SMC ZH vacuum ejector, Ø1.3 nozzle
Pneumatics · 18 ea free
18 — 18 — $96.00 $1,728
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
24 12 12 — $21.00 $504
IME12-04BPSZC0S SICK IME12 inductive proximity sensor
Sensors & safety · 36 ea free
6 — 6 — $58.00 $348
WTB4-3P2161 SICK WTB4 photoelectric sensor
Sensors & safety · 22 ea free
6 — 6 — $142.00 $852
TRK-CSS-M Compliance shock sensor — medium (≤150 kg tooling)
Trak products · 10 ea free
3 2 1 — $1,020.00 $3,060
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
3 2 1 — $145.00 $435
TRK-SLR-01 Vacuum slip ring — robot axis 6
Trak products · 4 ea free
3 2 1 — $1,240.00 $3,720
TRK-VFRM-AN Vacuum gripper frame — anodised aluminium (machined)
Trak products · 1 ea free
3 2 1 — $2,400.00 $7,200
PIAB-B75-2 Piab B75-2 bellows suction cup, NBR
Vacuum · 87 ea free
72 — 72 — $38.00 $2,736
PICOMPACT-23 Piab piCOMPACT23 vacuum pump, energy saving
Vacuum · 0 ea free
3 — 2 1
2 on order
$1,460.00 $4,380
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $50,40030% of $168,000
Deposit 30%
INV-10456
$50,400 ex GST · $55,440 inc
PaidXero synced
FAT 40%
$67,200
not raised
Commissioning 30%
$50,400
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 10 Aug 2026 25 Aug 2026 12 Daniel Pham
Procurement Procurement 20 Aug 2026 02 Sep 2026 10 Jess Taylor
Fabrication Excelfab — laser, fold & weld 28 Aug 2026 08 Sep 2026 8 Ben Nguyen
Assembly Gripper assembly bench 19 Oct 2026 03 Nov 2026 12 Ryan Walsh
Controls Controls & robot programming 26 Oct 2026 04 Nov 2026 8 Luke Brennan
FAT FAT cell 04 Nov 2026 05 Nov 2026 2 Matt O'Connor
Commissioning Site crew 24 Nov 2026 26 Nov 2026 3 Steve Hargreaves
Time booked
238.0 h · $21,731 at cost rates
Priya Raman108.0 h · $9,720
Daniel Pham62.0 h · $5,890
Ben Nguyen29.0 h · $2,146
Josh Mitchell24.0 h · $2,400
Luke Brennan15.0 h · $1,575
DateWhoTaskHoursCost
18 Sep 2026Priya RamanMechanical design 2.0$180
17 Sep 2026Priya RamanMechanical design 6.0$540
16 Sep 2026Priya RamanMechanical design 4.0$360
15 Sep 2026Daniel PhamMechanical design 4.0$380
14 Sep 2026Ben NguyenMachining & fit-up 1.0$74
14 Sep 2026Priya RamanMechanical design 4.0$360
11 Sep 2026Ben NguyenMachining & fit-up 4.0$296
11 Sep 2026Daniel PhamMechanical design 6.0$570
10 Sep 2026Ben NguyenMachining & fit-up 8.0$592
10 Sep 2026Daniel PhamMechanical design 7.5$713
09 Sep 2026Ben NguyenMachining & fit-up 8.0$592
09 Sep 2026Priya RamanMechanical design 8.0$720
08 Sep 2026Ben NguyenMachining & fit-up 4.0$296
08 Sep 2026Priya RamanMechanical design 4.0$360
07 Sep 2026Ben NguyenMachining & fit-up 4.0$296
07 Sep 2026Priya RamanMechanical design 8.0$720
04 Sep 2026Daniel PhamMechanical design 8.0$760
03 Sep 2026Priya RamanMechanical design 7.5$675
02 Sep 2026Priya RamanMechanical design 8.0$720
01 Sep 2026Daniel PhamMechanical design 6.0$570
31 Aug 2026Priya RamanMechanical design 7.5$675
28 Aug 2026Daniel PhamMechanical design 4.0$380
27 Aug 2026Daniel PhamMechanical design 7.5$713
26 Aug 2026Priya RamanMechanical design 4.0$360
25 Aug 2026Priya RamanMechanical design 8.0$720
24 Aug 2026Daniel PhamMechanical design 7.5$713
21 Aug 2026Daniel PhamMechanical design 4.0$380
20 Aug 2026Priya RamanMechanical design 8.0$720
19 Aug 2026Daniel PhamMechanical design 7.5$713
18 Aug 2026Priya RamanMechanical design 7.5$675
17 Aug 2026Luke BrennanControls design 3.0$315
17 Aug 2026Priya RamanMechanical design 8.0$720
14 Aug 2026Josh MitchellControls design 8.0$800
14 Aug 2026Priya RamanMechanical design 7.5$675
13 Aug 2026Luke BrennanControls design 4.0$420
13 Aug 2026Priya RamanMechanical design 6.0$540
12 Aug 2026Luke BrennanControls design 8.0$840
11 Aug 2026Josh MitchellControls design 8.0$800
10 Aug 2026Josh MitchellControls design 8.0$800
Project
Customer
Coca-Cola Europacific Partners
Andrew Fitzgerald · Engineering Manager — Moorebank
Site
Coca-Cola Europacific Partners — Moorebank
Robot
Motoman PL190 (existing)
PM
Sebastian
Quote
Q-26-0051
Customer PO
CCE-PO-4552092
Key dates
Start
10 Aug 2026
FAT
04 Nov 2026
Ship
11 Nov 2026
Commissioning
24 Nov 2026
Money
Value
$168,000
Budget cost
$125,939
Parts committed
$29,061
Parts issued
$9,930
Labour to date
$21,731
Forecast cost
$125,939
Forecast margin
$42,061 · 25.0%
Purchase orders
All POs
Calendar
Calendar
Activity
Quote Q-26-0051 won — project TA-26-033 opened.
31 Jul, 10:08am · Craig Kirkpatrick