Projects / TA-26-033
TA-26-033
Fabrication On trackVacuum palletising grippers ×3 — Lines 6–8 PET · Coca-Cola Europacific Partners · Vacuum palletising
Value
$168,000
budget cost $126k
Cost to date
$31,661
$10k parts · $22k labour
Forecast margin
25.0%
$42,061
Claimed
30%
$50,400 of $168,000
FAT
4 Nov
in 29 days
Parts short
1
all on order
Bill of materials
13 lines · $29,061 committed · reserved parts are held for this project, issued parts are on the machine
| Part no | Description | Qty | Issued | Reserved | Short | Unit | Line | |
|---|---|---|---|---|---|---|---|---|
| SHCS-M8-25 | Socket head cap screw M8 × 25, 12.9 (box 100) Fasteners · 18 box free | 3 | 2 | 1 | — | $34.00 | $102 | |
| KQ2H08-02AS | SMC push-in fitting 8 mm (bag 10) Pneumatics · 27 bag free | 6 | — | 6 | — | $21.00 | $126 | |
| VTUG-10-8M | Festo VTUG valve terminal, 8 stations, IO-Link Pneumatics · 5 ea free | 3 | — | 3 | — | $1,290.00 | $3,870 | |
| ZH13DS-06-06-08 | SMC ZH vacuum ejector, Ø1.3 nozzle Pneumatics · 18 ea free | 18 | — | 18 | — | $96.00 | $1,728 | |
| AL-PROF-4545 | Aluminium profile 45 × 45, per metre Raw material · 108 m free | 24 | 12 | 12 | — | $21.00 | $504 | |
| IME12-04BPSZC0S | SICK IME12 inductive proximity sensor Sensors & safety · 36 ea free | 6 | — | 6 | — | $58.00 | $348 | |
| WTB4-3P2161 | SICK WTB4 photoelectric sensor Sensors & safety · 22 ea free | 6 | — | 6 | — | $142.00 | $852 | |
| TRK-CSS-M | Compliance shock sensor — medium (≤150 kg tooling) Trak products · 10 ea free | 3 | 2 | 1 | — | $1,020.00 | $3,060 | |
| TRK-MP-ABB | Sensor mounting plate — ABB ISO 9409 flange Trak products · 10 ea free | 3 | 2 | 1 | — | $145.00 | $435 | |
| TRK-SLR-01 | Vacuum slip ring — robot axis 6 Trak products · 4 ea free | 3 | 2 | 1 | — | $1,240.00 | $3,720 | |
| TRK-VFRM-AN | Vacuum gripper frame — anodised aluminium (machined) Trak products · 1 ea free | 3 | 2 | 1 | — | $2,400.00 | $7,200 | |
| PIAB-B75-2 | Piab B75-2 bellows suction cup, NBR Vacuum · 87 ea free | 72 | — | 72 | — | $38.00 | $2,736 | |
| PICOMPACT-23 | Piab piCOMPACT23 vacuum pump, energy saving Vacuum · 0 ea free | 3 | — | 2 | 1 2 on order | $1,460.00 | $4,380 |
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $50,40030% of $168,000
Deposit 30%
INV-10456
$50,400 ex GST · $55,440 inc
PaidXero synced
FAT 40%
$67,200
not raised
Commissioning 30%
$50,400
not raised
Build schedule
Where this build sits on the workshop's resources
| Done | Stage | Resource | Start | Finish | Days | Who |
|---|---|---|---|---|---|---|
| Design | Design office | 10 Aug 2026 | 25 Aug 2026 | 12 | Daniel Pham | |
| Procurement | Procurement | 20 Aug 2026 | 02 Sep 2026 | 10 | Jess Taylor | |
| Fabrication | Excelfab — laser, fold & weld | 28 Aug 2026 | 08 Sep 2026 | 8 | Ben Nguyen | |
| Assembly | Gripper assembly bench | 19 Oct 2026 | 03 Nov 2026 | 12 | Ryan Walsh | |
| Controls | Controls & robot programming | 26 Oct 2026 | 04 Nov 2026 | 8 | Luke Brennan | |
| FAT | FAT cell | 04 Nov 2026 | 05 Nov 2026 | 2 | Matt O'Connor | |
| Commissioning | Site crew | 24 Nov 2026 | 26 Nov 2026 | 3 | Steve Hargreaves |
Time booked
238.0 h · $21,731 at cost rates
Priya Raman108.0 h · $9,720
Daniel Pham62.0 h · $5,890
Ben Nguyen29.0 h · $2,146
Josh Mitchell24.0 h · $2,400
Luke Brennan15.0 h · $1,575
| Date | Who | Task | Hours | Cost | |
|---|---|---|---|---|---|
| 18 Sep 2026 | Priya Raman | Mechanical design | 2.0 | $180 | |
| 17 Sep 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 16 Sep 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 15 Sep 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 14 Sep 2026 | Ben Nguyen | Machining & fit-up | 1.0 | $74 | |
| 14 Sep 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 11 Sep 2026 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 11 Sep 2026 | Daniel Pham | Mechanical design | 6.0 | $570 | |
| 10 Sep 2026 | Ben Nguyen | Machining & fit-up | 8.0 | $592 | |
| 10 Sep 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 09 Sep 2026 | Ben Nguyen | Machining & fit-up | 8.0 | $592 | |
| 09 Sep 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 08 Sep 2026 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 08 Sep 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 07 Sep 2026 | Ben Nguyen | Machining & fit-up | 4.0 | $296 | |
| 07 Sep 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 04 Sep 2026 | Daniel Pham | Mechanical design | 8.0 | $760 | |
| 03 Sep 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 02 Sep 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 01 Sep 2026 | Daniel Pham | Mechanical design | 6.0 | $570 | |
| 31 Aug 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 28 Aug 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 27 Aug 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 26 Aug 2026 | Priya Raman | Mechanical design | 4.0 | $360 | |
| 25 Aug 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 24 Aug 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 21 Aug 2026 | Daniel Pham | Mechanical design | 4.0 | $380 | |
| 20 Aug 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 19 Aug 2026 | Daniel Pham | Mechanical design | 7.5 | $713 | |
| 18 Aug 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 17 Aug 2026 | Luke Brennan | Controls design | 3.0 | $315 | |
| 17 Aug 2026 | Priya Raman | Mechanical design | 8.0 | $720 | |
| 14 Aug 2026 | Josh Mitchell | Controls design | 8.0 | $800 | |
| 14 Aug 2026 | Priya Raman | Mechanical design | 7.5 | $675 | |
| 13 Aug 2026 | Luke Brennan | Controls design | 4.0 | $420 | |
| 13 Aug 2026 | Priya Raman | Mechanical design | 6.0 | $540 | |
| 12 Aug 2026 | Luke Brennan | Controls design | 8.0 | $840 | |
| 11 Aug 2026 | Josh Mitchell | Controls design | 8.0 | $800 | |
| 10 Aug 2026 | Josh Mitchell | Controls design | 8.0 | $800 |
Project
- Customer
- Coca-Cola Europacific PartnersAndrew Fitzgerald · Engineering Manager — Moorebank
- Site
- Coca-Cola Europacific Partners — Moorebank
- Robot
- Motoman PL190 (existing)
- PM
- Sebastian
- Quote
- Q-26-0051
- Customer PO
- CCE-PO-4552092
Key dates
- Start
- 10 Aug 2026
- FAT
- 04 Nov 2026
- Ship
- 11 Nov 2026
- Commissioning
- 24 Nov 2026
Money
- Value
- $168,000
- Budget cost
- $125,939
- Parts committed
- $29,061
- Parts issued
- $9,930
- Labour to date
- $21,731
- Forecast cost
- $125,939
- Forecast margin
- $42,061 · 25.0%
Purchase orders
All POsCalendar
CalendarActivity
Quote Q-26-0051 won — project TA-26-033 opened.
31 Jul, 10:08am · Craig Kirkpatrick