TA-26-042 · Unilever Australia Demo Robot machine loading — carton blanks into case erectors
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-042

TA-26-042

Design On track

Robot machine loading — carton blanks into case erectors · Unilever Australia · Machine loading

Value
$398,000
budget cost $291k
Cost to date
$18,110
$0 parts · $18k labour
Forecast margin
26.2%
$104,455
Claimed
30%
$119,400 of $398,000
FAT
13 Jan
in 99 days
Parts short
2
2 not on order
Bill of materials
14 lines · $121,795 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CX5130-0125 Beckhoff CX5130 embedded PC (TwinCAT)
Drives & controls · 4 ea free
1 — 1 — $2,480.00 $2,480
IOL-MASTER-8 IO-Link master, 8 port, EtherCAT
Electrical · 4 ea free
1 — 1 — $1,060.00 $1,060
AL-PROF-4545 Aluminium profile 45 × 45, per metre
Raw material · 108 m free
12 — 12 — $21.00 $252
M410IC-185 FANUC M-410iC/185 palletising robot
Robots · 0 ea free
1 — — 1 $98,500.00 $98,500
C4P-SA15030A SICK deTec4 safety light curtain 1500 mm
Sensors & safety · 4 pair free
2 — 2 — $2,140.00 $4,280
PNOZ-MB0 Pilz PNOZmulti 2 safety relay base unit
Sensors & safety · 4 ea free
1 — 1 — $1,180.00 $1,180
WTB4-3P2161 SICK WTB4 photoelectric sensor
Sensors & safety · 22 ea free
6 — 6 — $142.00 $852
XG-DOOR-SL Axelent sliding door kit with interlock
Sensors & safety · 2 ea free
1 — 1 — $1,450.00 $1,450
XG-PANEL-2200 Axelent X-Guard mesh panel 2200 × 1500
Sensors & safety · 36 ea free
18 — 18 — $168.00 $3,024
XG-POST-2200 Axelent X-Guard post 2200
Sensors & safety · 36 ea free
16 — 16 — $64.00 $1,024
TRK-CSS-L Compliance shock sensor — large (≤300 kg tooling)
Trak products · 0 ea free
1 — — 1 $1,380.00 $1,380
TRK-MP-FAN Sensor mounting plate — FANUC flange
Trak products · 8 ea free
1 — 1 — $145.00 $145
PIAB-B75-2 Piab B75-2 bellows suction cup, NBR
Vacuum · 87 ea free
16 — 16 — $38.00 $608
GEH6060IL-31-B Zimmer GEH6060IL electric long-stroke gripper
Zimmer components · 0 ea free
2 — 2 — $2,780.00 $5,560
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $119,40030% of $398,000
Deposit 30%
INV-10467
$119,400 ex GST · $131,340 inc
Awaiting paymentXero synced
FAT 40%
$159,200
not raised
Commissioning 30%
$119,400
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 21 Sep 2026 16 Oct 2026 20 Priya Raman
Procurement Procurement 09 Oct 2026 29 Oct 2026 15 Jess Taylor
Fabrication Excelfab — laser, fold & weld 22 Oct 2026 06 Nov 2026 12 Ben Nguyen
Assembly Assembly bay 2 14 Dec 2026 12 Jan 2027 22 Ryan Walsh
Controls Controls & robot programming 25 Dec 2026 14 Jan 2027 15 Luke Brennan
FAT FAT cell 13 Jan 2027 15 Jan 2027 3 Matt O'Connor
Commissioning Site crew 10 Feb 2027 19 Feb 2027 8 Steve Hargreaves
Time booked
190.0 h · $18,110 at cost rates
Daniel Pham109.0 h · $10,355
Priya Raman45.5 h · $4,095
Luke Brennan22.0 h · $2,310
Josh Mitchell13.5 h · $1,350
DateWhoTaskHoursCost
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Priya RamanMechanical design 7.5$675
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Daniel PhamMechanical design 8.0$760
06 Oct 2026Daniel PhamMechanical design 4.0$380
05 Oct 2026Priya RamanMechanical design 8.0$720
02 Oct 2026Priya RamanMechanical design 8.0$720
01 Oct 2026Daniel PhamMechanical design 6.0$570
30 Sep 2026Daniel PhamMechanical design 7.5$713
29 Sep 2026Luke BrennanControls design 2.0$210
29 Sep 2026Daniel PhamMechanical design 7.5$713
28 Sep 2026Josh MitchellControls design 7.5$750
28 Sep 2026Daniel PhamMechanical design 4.0$380
25 Sep 2026Luke BrennanControls design 6.0$630
25 Sep 2026Daniel PhamMechanical design 6.0$570
24 Sep 2026Luke BrennanControls design 8.0$840
24 Sep 2026Daniel PhamMechanical design 4.0$380
23 Sep 2026Luke BrennanControls design 6.0$630
23 Sep 2026Daniel PhamMechanical design 7.5$713
22 Sep 2026Josh MitchellControls design 6.0$600
22 Sep 2026Priya RamanMechanical design 6.0$540
21 Sep 2026Daniel PhamMechanical design 6.0$570
Project
Customer
Unilever Australia
Rajesh Iyer · Automation Lead
Site
Unilever Australia — Minto
Robot
FANUC M-410iC/185
PM
Sebastian
Quote
Q-26-0060
Customer PO
UNI-PO-4574556
Key dates
Start
21 Sep 2026
FAT
13 Jan 2027
Ship
20 Jan 2027
Commissioning
10 Feb 2027
Money
Value
$398,000
Budget cost
$290,738
Parts committed
$121,795
Parts issued
$0
Labour to date
$18,110
Forecast cost
$293,545
Forecast margin
$104,455 · 26.2%
Purchase orders
All POs
No purchase orders for this project.
Calendar
Calendar
Activity
Quote Q-26-0060 won — project TA-26-042 opened.
13 Sep, 10:08am · Craig Kirkpatrick