Trak
Trak
TA-26-043 · Carlton & United Breweries Demo Pallet destrapping & debanding — glass line
Xero · synced 9:14am Tue 06 Oct 2026
Projects / TA-26-043

TA-26-043

Procurement On hold

Pallet destrapping & debanding — glass line · Carlton & United Breweries · Pallet destrapping / debanding

Value
$446,000
budget cost $337k
Cost to date
$36,848
$0 parts · $37k labour
Forecast margin
24.4%
$109,032
Claimed
30%
$133,800 of $446,000
FAT
2 Dec
in 57 days
Parts short
1
all on order
Bill of materials
17 lines · $122,127 committed · reserved parts are held for this project, issued parts are on the machine
Part noDescriptionQtyIssuedReservedShortUnitLine
CX5130-0125 Beckhoff CX5130 embedded PC (TwinCAT)
Drives & controls · 4 ea free
1 — 1 — $2,480.00 $2,480
EK1100 Beckhoff EK1100 EtherCAT coupler
Drives & controls · 8 ea free
2 — 2 — $215.00 $430
ENC-600-SS Control enclosure 600 × 600, stainless
Electrical · 2 ea free
1 — 1 — $920.00 $920
VTUG-10-8M Festo VTUG valve terminal, 8 stations, IO-Link
Pneumatics · 5 ea free
1 — 1 — $1,290.00 $1,290
SHS-50-3-8M Steel SHS 50 × 50 × 3, 8 m length
Raw material · 15 length free
4 — 4 — $96.00 $384
IRB460-110 ABB IRB 460 palletising robot, 110 kg / 2.4 m
Robots · 0 ea free
1 — — 1
1 on order
$92,400.00 $92,400
C4P-SA15030A SICK deTec4 safety light curtain 1500 mm
Sensors & safety · 4 pair free
2 — 2 — $2,140.00 $4,280
INSPECTORP621 SICK InspectorP621 vision sensor
Sensors & safety · 0 ea free
1 — 1 — $3,890.00 $3,890
PNOZ-MB0 Pilz PNOZmulti 2 safety relay base unit
Sensors & safety · 4 ea free
1 — 1 — $1,180.00 $1,180
WTB4-3P2161 SICK WTB4 photoelectric sensor
Sensors & safety · 22 ea free
4 — 4 — $142.00 $568
XG-DOOR-SL Axelent sliding door kit with interlock
Sensors & safety · 2 ea free
1 — 1 — $1,450.00 $1,450
XG-PANEL-2200 Axelent X-Guard mesh panel 2200 × 1500
Sensors & safety · 36 ea free
14 — 14 — $168.00 $2,352
XG-POST-2200 Axelent X-Guard post 2200
Sensors & safety · 36 ea free
12 — 12 — $64.00 $768
TRK-CHP-13 Strap chipper module — 13 mm cut
Trak products · 2 ea free
1 — 1 — $6,850.00 $6,850
TRK-CSS-M Compliance shock sensor — medium (≤150 kg tooling)
Trak products · 10 ea free
1 — 1 — $1,020.00 $1,020
TRK-MP-ABB Sensor mounting plate — ABB ISO 9409 flange
Trak products · 10 ea free
1 — 1 — $145.00 $145
GPP5013N-00-A Zimmer GPP5013N pneumatic parallel gripper
Zimmer components · 10 ea free
2 — 2 — $860.00 $1,720
Progress claims
30% on order · 40% on FAT sign-off · 30% on commissioning — each pushed to Xero when raised
Claimed $133,80030% of $446,000
Deposit 30%
INV-10468
$133,800 ex GST · $147,180 inc
OverdueXero synced
FAT 40%
$178,400
not raised
Commissioning 30%
$133,800
not raised
Build schedule
Where this build sits on the workshop's resources
Open schedule
DoneStageResourceStartFinishDaysWho
Design Design office 17 Aug 2026 11 Sep 2026 20 Priya Raman
Procurement Procurement 04 Sep 2026 24 Sep 2026 15 Jess Taylor
Fabrication Excelfab — laser, fold & weld 17 Sep 2026 02 Oct 2026 12 Ben Nguyen
Assembly Assembly bay 1 02 Nov 2026 01 Dec 2026 22 Ryan Walsh
Controls Controls & robot programming 13 Nov 2026 03 Dec 2026 15 Luke Brennan
FAT FAT cell 02 Dec 2026 04 Dec 2026 3 Matt O'Connor
Commissioning Site crew 27 Jan 2027 05 Feb 2027 8 Steve Hargreaves
Time booked
389.0 h · $36,848 at cost rates
Daniel Pham174.5 h · $16,578
Priya Raman141.5 h · $12,735
Luke Brennan47.0 h · $4,935
Josh Mitchell26.0 h · $2,600
DateWhoTaskHoursCost
06 Oct 2026Priya RamanMechanical design 6.0$540
06 Oct 2026Daniel PhamMechanical design 4.0$380
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Priya RamanMechanical design 7.5$675
06 Oct 2026Priya RamanMechanical design 7.5$675
06 Oct 2026Daniel PhamMechanical design 6.0$570
06 Oct 2026Daniel PhamMechanical design 8.0$760
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Priya RamanMechanical design 8.0$720
06 Oct 2026Daniel PhamMechanical design 7.5$713
06 Oct 2026Priya RamanMechanical design 8.0$720
06 Oct 2026Priya RamanMechanical design 4.0$360
06 Oct 2026Priya RamanMechanical design 7.5$675
06 Oct 2026Daniel PhamMechanical design 6.0$570
05 Oct 2026Daniel PhamMechanical design 8.0$760
02 Oct 2026Priya RamanMechanical design 8.0$720
01 Oct 2026Daniel PhamMechanical design 7.5$713
30 Sep 2026Priya RamanMechanical design 6.0$540
29 Sep 2026Daniel PhamMechanical design 8.0$760
28 Sep 2026Daniel PhamMechanical design 6.0$570
25 Sep 2026Priya RamanMechanical design 8.0$720
24 Sep 2026Priya RamanMechanical design 6.0$540
23 Sep 2026Priya RamanMechanical design 6.0$540
22 Sep 2026Daniel PhamMechanical design 7.5$713
21 Sep 2026Priya RamanMechanical design 4.0$360
18 Sep 2026Daniel PhamMechanical design 8.0$760
17 Sep 2026Daniel PhamMechanical design 8.0$760
16 Sep 2026Priya RamanMechanical design 8.0$720
15 Sep 2026Priya RamanMechanical design 4.0$360
14 Sep 2026Daniel PhamMechanical design 6.0$570
11 Sep 2026Priya RamanMechanical design 8.0$720
10 Sep 2026Priya RamanMechanical design 7.5$675
09 Sep 2026Priya RamanMechanical design 4.0$360
08 Sep 2026Daniel PhamMechanical design 6.0$570
07 Sep 2026Daniel PhamMechanical design 7.5$713
04 Sep 2026Daniel PhamMechanical design 6.0$570
03 Sep 2026Josh MitchellControls design 2.0$200
03 Sep 2026Daniel PhamMechanical design 6.0$570
02 Sep 2026Josh MitchellControls design 6.0$600
02 Sep 2026Daniel PhamMechanical design 6.0$570
01 Sep 2026Josh MitchellControls design 8.0$800
01 Sep 2026Priya RamanMechanical design 6.0$540
31 Aug 2026Luke BrennanControls design 8.0$840
31 Aug 2026Daniel PhamMechanical design 6.0$570
28 Aug 2026Luke BrennanControls design 6.0$630
28 Aug 2026Priya RamanMechanical design 4.0$360
27 Aug 2026Luke BrennanControls design 4.0$420
27 Aug 2026Priya RamanMechanical design 7.5$675
26 Aug 2026Luke BrennanControls design 7.5$788
26 Aug 2026Priya RamanMechanical design 6.0$540
25 Aug 2026Luke BrennanControls design 4.0$420
25 Aug 2026Daniel PhamMechanical design 4.0$380
24 Aug 2026Luke BrennanControls design 7.5$788
24 Aug 2026Daniel PhamMechanical design 7.5$713
21 Aug 2026Luke BrennanControls design 4.0$420
21 Aug 2026Daniel PhamMechanical design 4.0$380
20 Aug 2026Josh MitchellControls design 6.0$600
20 Aug 2026Daniel PhamMechanical design 8.0$760
19 Aug 2026Josh MitchellControls design 4.0$400
19 Aug 2026Daniel PhamMechanical design 8.0$760
Project
Customer
Carlton & United Breweries
Scott McKenzie · Packaging Engineering Manager
Site
Carlton & United Breweries — Abbotsford
Robot
ABB IRB 460
PM
Sebastian
Quote
Q-26-0061
Customer PO
CUB-PO-4595980
Key dates
Start
17 Aug 2026
FAT
02 Dec 2026
Ship
09 Dec 2026
Commissioning
27 Jan 2027
Money
Value
$446,000
Budget cost
$336,968
Parts committed
$122,127
Parts issued
$0
Labour to date
$36,848
Forecast cost
$336,968
Forecast margin
$109,032 · 24.4%
Notes

CUB moved their shutdown to late January. Holding procurement of the robot until the PO variation is signed.

Purchase orders
All POs
Calendar
Calendar
Nothing in the calendar.
Activity
Quote Q-26-0061 won — project TA-26-043 opened.
10 Aug, 10:53am · Craig Kirkpatrick