Build schedule
Every live build across the design office, Excelfab, the assembly bays, the FAT cell and the site crew. Drag a bar to move it; drag its right edge to change its length.
Open tasks
69
16 live projects
FATs in next 4 weeks
6
in the FAT cell
Clashes
1
double-booked resources
Busiest resource
Assembly bay 1
17 of the next 20 working days booked
Clashes
Drag one of the bars so they no longer share a day — the clash clears on its own.
Resource
Design office
Procurement
Excelfab — laser, fold & weld
Gripper assembly bench
Assembly bay 1 1 at a time
Assembly bay 2 1 at a time
Controls & robot programming
FAT cell 1 at a time
Site crew
Tue 27 OctMon 2 NovMon 9 NovMon 16 NovMon 23 NovMon 30 NovMon 7 DecMon 14 DecMon 21 DecMon 28 Dec
27282930234569101112131617181920232425262730123478910111415161718212223242528
On trackAt riskLateOn hold Clash Left edge = project health · click a bar to edit
Design office
TA-26-034Design 14 Sep – 9 Oct TA-26-042Design 21 Sep – 16 Oct TA-26-045Design 28 Sep – 13 Oct TA-26-047Design 28 Sep – 13 Oct Procurement
TA-26-034Procurement 2 Oct – 22 Oct TA-26-045Procurement 8 Oct – 21 Oct TA-26-047Procurement 8 Oct – 21 Oct TA-26-042Procurement 9 Oct – 29 Oct Excelfab — laser, fold & weld
TA-26-046Fabrication 25 Sep – 6 Oct TA-26-034Fabrication 15 Oct – 30 Oct TA-26-045Fabrication 16 Oct – 27 Oct TA-26-047Fabrication 16 Oct – 27 Oct TA-26-042Fabrication 22 Oct – 6 Nov Gripper assembly bench
TA-26-044Assembly 25 Sep – 12 Oct TA-26-037Assembly 28 Sep – 13 Oct TA-26-041Assembly 5 Oct – 20 Oct TA-26-046Assembly 9 Oct – 22 Oct TA-26-033Assembly 19 Oct – 3 Nov TA-26-036Assembly 2 Nov – 17 Nov TA-26-045Assembly 19 Nov – 4 Dec TA-26-038Assembly 23 Nov – 8 Dec Assembly bay 1
TA-26-031Assembly 28 Sep – 27 Oct TA-26-043Assembly 2 Nov – 1 Dec TA-26-034Assembly 21 Dec – 19 Jan Assembly bay 2
TA-26-042Assembly 14 Dec – 12 Jan Controls & robot programming
TA-26-044Controls 2 Oct – 13 Oct TA-26-037Controls 5 Oct – 14 Oct TA-26-031Controls 9 Oct – 29 Oct TA-26-041Controls 12 Oct – 21 Oct TA-26-046Controls 15 Oct – 23 Oct TA-26-033Controls 26 Oct – 4 Nov TA-26-036Controls 9 Nov – 18 Nov TA-26-043Controls 13 Nov – 3 Dec FAT cell
TA-26-035FAT 8 Oct – 9 Oct TA-26-044FAT 13 Oct – 14 Oct TA-26-037FAT 14 Oct – 15 Oct TA-26-041FAT 21 Oct – 22 Oct TA-26-046FAT 23 Oct – 26 Oct TA-26-031FAT 28 Oct – 30 Oct TA-26-033FAT 4 Nov – 5 Nov TA-26-036FAT 18 Nov – 19 Nov Site crew
TA-26-039Commissioning 12 Oct – 21 Oct TA-26-035Commissioning 21 Oct – 23 Oct TA-26-044Commissioning 26 Oct – 28 Oct TA-26-040Commissioning 27 Oct – 5 Nov TA-26-037Commissioning 28 Oct – 30 Oct TA-26-041Commissioning 29 Oct – 2 Nov TA-26-046Commissioning 9 Nov – 11 Nov TA-26-033Commissioning 24 Nov – 26 Nov This week
5 Oct – 9 Oct
Design office
TA-26-034 Design Opal Australian Paper · Priya Raman TA-26-042 Design Unilever Australia · Priya Raman TA-26-045 Design Visy Technology Systems · Daniel Pham TA-26-047 Design Bega Cheese · Daniel Pham Procurement
TA-26-034 Procurement Opal Australian Paper · Jess Taylor TA-26-045 Procurement Visy Technology Systems · Jess Taylor TA-26-047 Procurement Bega Cheese · Jess Taylor TA-26-042 Procurement Unilever Australia · Jess Taylor Excelfab — laser, fold & weld
TA-26-046 Fabrication Lion — Lidcombe Brewery · Ben Nguyen Gripper assembly bench
TA-26-044 Assembly Saputo Dairy Australia · Tom Kowalski TA-26-037 Assembly Scott Automation & Robotics · Ryan Walsh TA-26-041 Assembly Bosch Manufacturing Solutions · Tom Kowalski TA-26-046 Assembly Lion — Lidcombe Brewery · Ryan Walsh Assembly bay 1
TA-26-031 Assembly Asahi Beverages · Tom Kowalski